Multiple Choice
The most pessimistic time for a task is 9 months.The most optimistic time for the same task is 7 months.What is the variance,in months,for the duration of the activity?
A) 0.01
B) 0.11
C) 1.01
D) 2.31
Correct Answer:

Verified
Correct Answer:
Verified