In Considering Whether We Should Crash a Project,we Should ______

Question 72

Multiple Choice

In considering whether we should crash a project,we should ______.


A) assess the costs associated with each of the project's activities
B) accelerate those tasks that will have the most impact on the schedule for the least cost
C) both A and B
D) neither A nor B

Correct Answer: