Multiple Choice
If the standard deviation is 3.5,the Z value is 1.0,and the expected date of completion is 30 weeks,then the due date for project completion is ______.
A) 33.5 weeks
B) 41.5 weeks
C) 21.95 weeks
D) 38.55 weeks
Correct Answer:

Verified
Correct Answer:
Verified