Which of the following statements is FALSE with regard to costs of crashing activities in a project?
A) As each project activity is crashed in order,the overall project budget increases.
B) It is usually necessary to crash all activities in a project.
C) Crashing additional activities beyond a point merely adds costs to the budget.
D) It may not be possible to crash all activities in a project.