If the Most Optimistic Time for Completing an Activity Is

Question 68

Multiple Choice

If the most optimistic time for completing an activity is 20,the most likely time is 22,and the most pessimistic time is 36,then the estimated time for the activity is ______.


A) 24
B) 34
C) 12
D) 29