Multiple Choice
If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 15 weeks is ______.
A) close to zero
B) half
C) more than 75%
D) less than 25%
Correct Answer:

Verified
Correct Answer:
Verified