Solved

A Project Consists of Four Activities with Information as Shown

Question 5

Multiple Choice

A project consists of four activities with information as shown in the table.What is the overall variance of the project?  Standard  Activity  Predecessor  Length  Deviation  A 102 B  A 121 C  B 162 D  C 143\begin{array}{|l|l|l|l|}\hline&&&\text { Standard }\\ \text { Activity } & \text { Predecessor } & \text { Length } & \begin{array}{l}\text { Deviation }\end{array} \\\hline \text { A } & - & 10 & 2 \\\hline \text { B } & \text { A } & 12 & 1 \\\hline \text { C } & \text { B } & 16 & 2 \\\hline \text { D } & \text { C } & 14 & 3\\\hline \end{array}


A) 18
B) 8
C) 2.82
D) 5.56

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions