Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology?  Activity  Predecessor  Length  Activity  Predecessor  Length A20DB16B A 20EC8C A 10 FD,E8\begin{array} { | l | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Activity } & \text { Predecessor } & \text { Length } \\\hline \mathrm { A } & - & 20 & \mathrm { D } & \mathrm { B } & 16 \\\hline \mathrm { B } & \text { A } & 20 & \mathrm { E } & \mathrm { C } & 8 \\\hline \mathrm { C } & \text { A } & 10 & \mathrm {~F} & \mathrm { D } , \mathrm { E } & 8\\\hline\end{array}


A) 9.0
B) 7.5
C) 4.5
D) 6.0

Correct Answer:

verifed

Verified