Multiple Choice
Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) The project manager cannot force subcontractors to use this project management approach.
B) The feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) Subcontractors routinely operate according to calendar delivery dates.
D) The corporate culture of "no blame" does not naturally extend to subcontractors.
Correct Answer:

Verified
Correct Answer:
Verified