Solved

An Assumption of the PERT Method Is

Question 16

Multiple Choice

An assumption of the PERT method is:


A) Activity times are not constant.
B) There is uncertainty in individual activity time estimates.
C) Distribution of project completion times and the probability that each activity is on the critical path can be computed.
D) All of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions