PERT assumes that the statistical variation in total project completion times can be computed by adding the standard deviations along the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: The critical path of the following network

Q13: The job of the project manager is

Q14: The information calculated from the forward and

Q15: Multiple critical paths can exist under the

Q16: An assumption of the PERT method is:<br>A)Activity

Q18: The advantage(s)that the Gantt chart has over

Q19: Which of the following statements is NOT

Q20: Project management requires:<br>A)Scheduling,planning,and controlling<br>B)Quantitative skills<br>C)Behavioral skills<br>D)All of

Q21: Given the list of activities,the expected

Q22: Critical path method (CPM)network scheduling assumes a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines