Multiple Choice
The advantage(s) that the Gantt chart has over the network method is (are) :
A) A Gantt chart is easy to use and quite widely understood.
B) Gantt charts show precedence relationships more explicitly than network scheduling.
C) Gantt charts require specialized training.
D) All of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q13: The job of the project manager is
Q14: The information calculated from the forward and
Q15: Multiple critical paths can exist under the
Q16: An assumption of the PERT method is:<br>A)Activity
Q17: PERT assumes that the statistical variation in
Q19: Which of the following statements is NOT
Q20: Project management requires:<br>A)Scheduling,planning,and controlling<br>B)Quantitative skills<br>C)Behavioral skills<br>D)All of
Q21: Given the list of activities,the expected
Q22: Critical path method (CPM)network scheduling assumes a
Q25: A forward pass is required while computing