Multiple Choice
Which of the following statements is NOT true about the PERT method of project scheduling?
A) PERT requires three time estimates for scheduling a given activity.
B) PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C) PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q14: The information calculated from the forward and
Q15: Multiple critical paths can exist under the
Q16: An assumption of the PERT method is:<br>A)Activity
Q17: PERT assumes that the statistical variation in
Q18: The advantage(s)that the Gantt chart has over
Q20: Project management requires:<br>A)Scheduling,planning,and controlling<br>B)Quantitative skills<br>C)Behavioral skills<br>D)All of
Q21: Given the list of activities,the expected
Q22: Critical path method (CPM)network scheduling assumes a
Q24: "Slack" refers to the difference between:<br>A)Late and
Q25: A forward pass is required while computing