Given the List of Activities,the Expected Time Estimates,and Variances,compute the Probability
Multiple Choice
Given the list of activities,the expected time estimates,and variances,compute the probability that the project time will be less than 30 minutes.Round Z to two decimals.
A) 0.6950
B) 0.7500
C) 0.8907
D) 0.9082
E) 0.9989
Correct Answer:

Verified
Correct Answer:
Verified
Q16: An assumption of the PERT method is:<br>A)Activity
Q17: PERT assumes that the statistical variation in
Q18: The advantage(s)that the Gantt chart has over
Q19: Which of the following statements is NOT
Q20: Project management requires:<br>A)Scheduling,planning,and controlling<br>B)Quantitative skills<br>C)Behavioral skills<br>D)All of
Q22: Critical path method (CPM)network scheduling assumes a
Q24: "Slack" refers to the difference between:<br>A)Late and
Q25: A forward pass is required while computing
Q25: Controlling a project does NOT include:<br>A)Monitoring costs,time,and
Q26: Which of the following statements about critical