Multiple Choice
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s) .
-Refer to the scenario above. Which of these activities has slack?
A) G
B) E
C) F
D) D
Correct Answer:

Verified
Correct Answer:
Verified
Q55: What is the latest that activity D
Q56: A project is composed of 6
Q57: The tablet unearthed by the archaeologist
Q58: In what way are projects and typical
Q59: Given the earliest and latest finish
Q60: A Gantt chart provides both a planning
Q62: Complete this table containing earliest and
Q63: The actual work gets done during the
Q64: An activity's duration added to its earliest
Q65: The earliest finish time of an activity