Complete this table containing earliest and latest start times and activity lengths.
 Activity  Predecessor  Length  Earliest Start  Earliest Finish  Latest Start  Latest  Finish  A 1111011 B  A 111720 C  B, D 302030 D  A 11201120 E  D 430 F  C, E, G 1030 G  A 112030\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \begin{array} { c } \text { Latest } \\\text { Finish }\end{array} \\\hline \text { A } & - & 11 & & 11 & 0 & 11 \\\hline \text { B } & \text { A } & & 11 & 17 & & 20 \\\hline \text { C } & \text { B, D } & & & 30 & 20 & 30 \\\hline \text { D } & \text { A } & & 11 & 20 & 11 & 20 \\\hline \text { E } & \text { D } & 4 & & & & 30 \\\hline \text { F } & \text { C, E, G } & 10 & & & 30 & \\\hline \text { G } & \text { A } & & 11 & 20 & & 30 \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | c | c | c | ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions