Multiple Choice
Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then
A) adding it from the values of total slack for the other activities also entering into that same activity.
B) subtracting it from the values of total slack for the other activities succeeding after that same activity.
C) subtracting it from the values of total slack for the other activities also entering into that same activity.
D) adding it from the values of total slack for the other activities succeeding after that same activity.
Correct Answer:

Verified
Correct Answer:
Verified
Q76: If _ is positive, it represents the
Q77: Each time the schedule is recalculated in
Q78: The project team can progressively elaborate the
Q79: Changes might be initiated by the customer
Q80: The estimated activity resources will also be
Q82: With respect to the project schedule, changes
Q83: Calculate the earliest start for Task D
Q84: In order to establish a basis from
Q85: The ES and EF times are determined
Q86: The amount of _ should determine the