Solved

Use the Information in the Table to Sketch the Network

Question 25

Essay

Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor  A 8 B 4 A  C 5 B, F  D 12 A E8 D  F 4 D G9 E, F \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 8 & \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 5 & \text { B, F } \\\hline \text { D } & 12 & \text { A } \\\hline E & 8 & \text { D } \\\hline \text { F } & 4 & \text { D } \\\hline G & 9 & \text { E, F } \\\hline\end{array}

Correct Answer:

verifed

Verified

The early and late s...