Use the Values in the Table to Calculate Activity Durations

Question 28

Essay

Use the values in the table to calculate activity durations and variances for the project.What is the project deadline such that there is a 75% chance it is completed on time? Use the values in the table to calculate activity durations and variances for the project.What is the project deadline such that there is a 75% chance it is completed on time?

Correct Answer:

verifed

Verified

The critical path is ACGIKL and has an e...