Multiple Choice
Often, the sum of the initial estimated costs is greater than the amount of funds budgeted by the sponsor.What should be done to arrive at an acceptable budget amount?
A) Cut the cost of the highest priced activity in half until the budget is reached.
B) Trade experienced and efficient resources for less experienced and less efficient resources.
C) Revise the budget expecting that several iterations may need to be made to reduce the costs.
D) Extend the scope of the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q40: The _ is the amount that is
Q41: Committed costs in a project are<br>A) those
Q42: If the cumulative earned value is $10
Q43: Cost estimates should be unreasonable and excessive.
Q44: In many projects, large dollar amounts are
Q46: The to-complete performance index is<br>A) the amount
Q47: The actual cost on a project is<br>A)
Q48: A second method for determining the forecasted
Q49: The _ is the amount that was
Q50: To keep track of _, it's necessary