Multiple Choice
Calculate the cost variance if the cumulative earned value is $10 and the cumulative actual costs are $20.
A) $10
B) -$10
C) 0.5
D) 2.0
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q79: What is the cost variance for a
Q80: A cost performance index greater than 1.0
Q81: The contractor's outflow of cash can be
Q82: The key to managing cash flow is
Q83: Based on analysis of actual cost it
Q85: The estimated cost of an activity should
Q86: The total project cost is often estimated
Q87: It is good practice to have the
Q88: It may be easier to estimate the
Q89: Committed costs need to be treated in