Assume two activities,printing and binding.Printing is a predecessor of binding.If printing is _______,then binding will start late by whatever amount of lateness is bequeathed to it by printing.
A) necessary
B) early
C) late
D) time-neutral
Correct Answer:

Verified
Correct Answer:
Verified