Joe and his team have been given a fixed budget and a time frame for the development of a new product.The team's key concern is that the development is likely to overshoot the given budget and time frame.Which of the following categories of risk is likely to be faced by Joe and his team?


A) Strategic risk
B) Market risk
C) Internal risk
D) Credit risk

Correct Answer: