Multiple Choice
Table 3.7
-Using Table 3.7,suppose activity D can be shortened from 4 weeks to 1 week.Assume all other activity times remain the same.How much shorter will the total project earliest completion time become?
A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 weeks
Correct Answer:

Verified
Correct Answer:
Verified