Multiple Choice
The purpose of performing a forward pass is to:
A) Identify the critical path
B) Determine the early start and the early finish times
C) Determine the late start and the late finish times
D) Determine the slack available in the process
E) All of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q4: The project management concept that can be
Q5: Gantt charts are effective if:<br>A)Activities are highly
Q6: The job of the project manager is
Q7: CPM network scheduling assumes a second order
Q8: The advantage(s)of the network method over the
Q9: An assumption of PERT is:<br>A)Activity times are
Q10: The advantage(s)that Gantt chart has over the
Q11: Which of the following statements about CPM
Q17: PERT assumes that the statistical variation in
Q20: Project management requires:<br>A)Scheduling,planning,and controlling<br>B)Quantitative skills<br>C)Behavioral skills<br>D)All of