Exam 6: Resource Utilization
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
A resource requirements plan illustrates
Free
(Multiple Choice)
4.8/5
(29)
Correct Answer:
C
Resource-limited scheduling is a method for
Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
D
When planning a project, it is necessary to estimate
Free
(Multiple Choice)
4.8/5
(28)
Correct Answer:
B
Technical constraints for a project are represented in a network diagram by
(Multiple Choice)
4.9/5
(34)
Resource leveling uses a trial-and-error method to test delaying
(Multiple Choice)
4.8/5
(37)
A project requires at least 28 worker-days to complete the project.What is the shortest time estimate for completion if the project is constrained to two workers per day? Assume no task requires more than one worker and the tasks can be completed independent of each other.
(Multiple Choice)
4.9/5
(35)
Resource requirements graphs based on an as-soon-as-possible schedule are drawn
(Multiple Choice)
4.7/5
(45)
At a minimum, network diagrams illustrate the ____ constraints among activities.
(Multiple Choice)
5.0/5
(36)
____ assist with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.
(Multiple Choice)
4.9/5
(40)
Resource leveling attempts to establish a schedule in which resource utilization is made as level as possible
(Multiple Choice)
4.9/5
(32)
If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days.The tasks can be completed independently of each other.If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
(Multiple Choice)
4.9/5
(39)
Resource utilization charts based on each activity's latest start time are said to be based on an ____ schedule.
(Multiple Choice)
4.9/5
(32)
Which of the following is likely not to be a process in a project management information system?
(Multiple Choice)
4.9/5
(35)
The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because
(Multiple Choice)
4.9/5
(39)
If resources are to be considered in planning, it is necessary to
(Multiple Choice)
4.8/5
(32)
Resources are not usually hired on a day-to-day basis to meet fluctuating requirements.This means that
(Multiple Choice)
4.8/5
(31)
In ____, when several activities need the same limited resource at the same time, the activities with the least slack have first priority.
(Multiple Choice)
4.7/5
(38)
___ is a method for developing the shortest schedule when the number or amount of available resources is fixed.
(Multiple Choice)
4.9/5
(36)
Resource constraints are represented in the network diagram by
(Multiple Choice)
4.8/5
(38)
A project is resource leveled without resource-limited constraints and the project did not extend beyond its required completion after leveling.Which of the following must have been false?
(Multiple Choice)
4.8/5
(33)
Showing 1 - 20 of 45