As part of, or in addition to, the documents in the archive, it can be valuable to create a database of common data elements from past projects in order to analyze and determine if there are trends or correlations that could be helpful in bidding, planning, and/or performing future projects.

Free
(True/False)
4.8/5
(26)
Correct Answer:
Verified

True

Feedback from the customer is important for the organization at the end of the project for all of the following reasons except

Free
(Multiple Choice)
4.8/5
(29)
Correct Answer:
Verified

D

Lessons learned could be helpful in bidding, planning, and/or performing future projects.

Free
(True/False)
4.8/5
(34)
Correct Answer:
Verified

True

Projects also can be terminated by the sponsor or customer.

(True/False)
4.9/5
(41)

Documentation of lessons learned should be done on an ongoing basis throughout the planning and performing phases of the project.

(True/False)
4.9/5
(35)

The process of closing the project involves various actions, including

(Multiple Choice)
4.7/5
(33)

As part of, or in addition to, the documents in the archive, it can be valuable to create a database of common data elements from past projects in order to analyze and determine if there are trends or correlations that

(Multiple Choice)
4.7/5
(28)

Successful projects should end with

(Multiple Choice)
4.8/5
(33)

During the final group meeting for the project, the project team should discuss all of the following except

(Multiple Choice)
4.9/5
(33)

The fourth phase of the project life cycle involves ____ the project.

(Multiple Choice)
4.9/5
(39)

Participants of ____ should include the project manager, key project team members, and key representatives of the customer's organization who were involved with the project.

(Multiple Choice)
4.8/5
(39)

The project organization should establish a ____ that includes an easily accessible repository that encourages project managers and teams to retrieve lessons learned and information from previous projects.

(Multiple Choice)
4.8/5
(31)

The process of closing the project involves various actions, including

(Multiple Choice)
4.9/5
(37)

Which of the following is the most likely the short-term result of a project being terminated early by a customer?

(Multiple Choice)
4.9/5
(34)

Hold ____ meetings at the end of the project with team members to have feedback from each team member about their performance and how to improve future projects.

(Multiple Choice)
4.9/5
(25)

There may be circumstances that require a project to be terminated before it is completed.

(True/False)
4.8/5
(34)

During the ____, review and evaluate performance of the project and identify what can be done to improve performance on future projects.

(Multiple Choice)
4.8/5
(39)

Projects also can be terminated by the sponsor or customer for financial situations.

(True/False)
4.8/5
(34)

Just as important as having the internal post-project meetings within the project organization is having a post-project evaluation meeting with the customer or sponsor.

(True/False)
4.8/5
(37)

Projects also can be terminated by the sponsor or customer because the project needs have changed.

(True/False)
4.8/5
(44)