Exam 5: Developing the Schedule
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
Total slack is calculated for each of the activities by finding the difference between
Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
C
If the project needs accelerated, efforts should be concentrated on
Free
(Multiple Choice)
4.9/5
(29)
Correct Answer:
C
The ____ involves regularly gathering data on project performance, comparing actual performance to planned performance, and taking corrective actions if actual performance is behind planned performance.
Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
B
The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and
(Multiple Choice)
4.8/5
(31)
Having the person who will be responsible for performing a specific activity estimate the duration for that activity ____ from that person and ____ that may be introduced by having one person estimate the durations for all of the activities.
(Multiple Choice)
4.8/5
(33)
Latest finish time (LF)is the latest time by which a specific activity must be
(Multiple Choice)
4.8/5
(38)
It is important to know what types of resources are available, in what quantities, and during what time periods to determine
(Multiple Choice)
4.8/5
(36)
Throughout the performance of the project, some activities will take longer than their estimated duration, others will be done in less time than their estimated duration, and
(Multiple Choice)
4.8/5
(38)
The development team develops, delivers, and demonstrates ____ during a sprint.
(Multiple Choice)
4.8/5
(34)
A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
(Multiple Choice)
4.8/5
(33)
The project control process starts with establishing a ____.
(Multiple Choice)
4.8/5
(28)
With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:
(Multiple Choice)
4.7/5
(31)
Schedule control involves four steps.List the four steps in order.
(Short Answer)
5.0/5
(33)
Schedule control involves four steps.Place these steps in their proper order by stating the letter sequence of their proper order.
A.Analyzing the schedule to determine which areas may need corrective action
B.Recalculating the schedule to evaluate the effects of the planned corrective actions
C.Revising the plan to incorporate the chosen corrective actions
D.Deciding what specific corrective actions should be taken
(Multiple Choice)
4.8/5
(27)
Padding estimates with the vision of becoming a hero when the activities are completed in less time than estimated is not a good practice.
(True/False)
4.9/5
(37)
Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of
(Multiple Choice)
4.8/5
(44)
Showing 1 - 20 of 127
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)