Exam 14: Performance Measurement Along the Supply Chain
Exam 1: Introduction to Supply Chain Management52 Questions
Exam 2: Purchasing Management52 Questions
Exam 3: Creating and Managing Supplier Relationships52 Questions
Exam 4: Ethical and Sustainable Sourcing51 Questions
Exam 5: Demand Forecasting52 Questions
Exam 6: Resource Planning Systems52 Questions
Exam 7: Inventory Management52 Questions
Exam 8: Process Management: Lean and Six Sigma in the Supply Chain52 Questions
Exam 9: Domestic U.S.and Global Logistics52 Questions
Exam 10: Customer Relationship Management52 Questions
Exam 11: Global Location Decisions52 Questions
Exam 12: Service Response Logistics54 Questions
Exam 13: Supply Chain Process Integration52 Questions
Exam 14: Performance Measurement Along the Supply Chain52 Questions
Select questions type
Which of the following is focused on integrating supply chains and measuring partner performance?
(Multiple Choice)
4.7/5
(38)
Which of the following questions needs to be answered before designing the appropriate product/service to fulfill customer service expectations:
(Multiple Choice)
4.9/5
(34)
How can using organizational costs,revenues,and profitability measures be ineffective or even damaging in managing a process,system,or organization?
(Essay)
4.8/5
(35)
According to the SCOR model,which of the following is NOT one of the five supply chain operation process categories?
(Multiple Choice)
4.7/5
(38)
While profit,revenue,and cost related metrics would seem to be useful in moving a company in the right direction,they are often difficult to tie to the good or poor behaviors of individual functional units or individual organizational processes.
(True/False)
4.8/5
(38)
The textbook described 7 supply chain specific performance measures.List three of those metrics.
(Essay)
4.9/5
(42)
A company produces 750 bicycles every day.Each bicycle is worth $250.The inputs used to make those bicycles are labor,materials,and machine costs.The company pays their employees a total of $7500 per day,the materials to make those bicycles cost $75 per bike,and the cost to operate the machines is $2500 per day.Based only on the data provided,what is this company's total productivity for one day?
(Multiple Choice)
4.9/5
(25)
Explain the difference between Total Productivity and Labor productivity.
(Essay)
4.9/5
(33)
When utilizing performance standards,the difference between the standard and the actual performance is called:
(Multiple Choice)
4.7/5
(31)
Which of the following BSC framework perspectives deals with new product development,innovative elements of processes,and time-based measures?
(Multiple Choice)
4.8/5
(39)
A model used for integrating supply chains and measuring partner performance is the SCOR model which separates supply chain operations into four categories: Sourcing,Costs,Operations,and Returns.
(True/False)
4.9/5
(36)
Some researchers have indicated that the Balanced Scorecard approach can problematic and costly to implement,and even after implementation may be unsuccessful in achieving the overall objectives.
(True/False)
4.8/5
(32)