A project can be defined as a set of complex interrelated tasks with different requirements regarding activity time and resources, but with a high degree of repetitiveness.

(True/False)
4.9/5
(38)

The term calendar is used in project management to keep track of the days and hours required for completion of projects.

(True/False)
4.8/5
(31)

Which one of the following is not considered a source of variance on the earned value chart?

(Multiple Choice)
4.9/5
(42)

The four sequential stages of team development include all but one of the following:

(Multiple Choice)
4.7/5
(32)

The term Late Finish refers to the latest time an activity can begin without delaying the completion of the project.

(True/False)
4.9/5
(40)

Before calculating a Late Start time for an activity, the Late Finish time must be known.

(True/False)
5.0/5
(26)

Which one of the following is not a critical time estimate for a Beta distribution?

(Multiple Choice)
4.8/5
(37)

Gantt project charts are useful for all but one of the following reasons:

(Multiple Choice)
4.8/5
(45)

It is possible to delay the start of a non-critical activity and, in the process, make a following activity critical.

(True/False)
4.9/5
(30)

Which one of the following is not an objective of activity crashing?

(Multiple Choice)
4.8/5
(39)

Projects are terminated for all but one of the following reasons:

(Multiple Choice)
4.9/5
(41)

A major flaw in critical path analysis with uncertain activity times is the conservative nature of the expected project completion time.

(True/False)
4.9/5
(39)

Estimates of project expected completion time and variance usually are not biased when based on the single critical path.

(True/False)
4.9/5
(34)

Merge node bias occurs where the project network contains non-critical paths with small total slack times.

(True/False)
5.0/5
(40)

Schedule variance is the difference between budgeted cost for work performed and actual cost of work performed.

(True/False)
4.9/5
(42)

Which of the following is not true about a critical path in a project network with certain activity times?

(Multiple Choice)
4.9/5
(38)

When crashing activities for construction projects, the contractor's minimum cost duration might not coincide with the client's target completion date.

(True/False)
4.7/5
(42)

Monte Carlo simulation of project networks is not recommended when:

(Multiple Choice)
4.8/5
(35)

The critical path refers to the sequence of activities that represent the longest time path through a project network.

(True/False)
4.9/5
(47)

Implementing critical path analysis is faced with all but one of the following problems:

(Multiple Choice)
4.8/5
(36)
Showing 21 - 40 of 40