Exam 18: Statistical Applications in Quality Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

TABLE 18-7 A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes samples of size 5 from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below. Sheet Day 1 2 3 4 5 Mean Range 1 8 10 14 6 5 8.6 9 2 8 13 6 6 10 8.6 7 3 10 12 7 7 9 9.0 5 4 5 9 12 7 10 8.6 7 5 8 3 8 9 10 7.6 7 6 9 7 9 6 9 8.0 3 7 10 10 5 7 6 7.6 5 8 10 9 10 6 5 8.0 5 9 6 10 6 9 9 8.0 4 10 6 9 8 6 8 7.4 3 11 8 5 6 10 10 7.8 5 12 6 4 7 7 12 7.2 8 13 7 5 7 6 9 6.8 4 14 5 8 8 7 6 6.8 3 15 7 12 10 6 10 9.0 6 16 7 11 4 7 8 7.4 7 17 8 4 5 4 7 5.6 4 18 11 4 11 11 10 9.4 7 19 6 10 6 10 10 8.4 4 20 6 12 12 6 8 8.8 6 She also decides that the upper specification limit is 10 blemishes. -Referring to Table 18-7, an R chart is to be constructed for the number of blemishes. One way to create the lower control limit involves multiplying the average of the sample ranges by D3. For this data set, the value of D3 is ____ .

(Short Answer)
4.8/5
(37)

TABLE 18-4 A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour R 1 18.4 25 2 16.9 27 3 23.0 30 4 21.2 23 5 21.0 24 6 24.0 25 7 19.3 12 8 15.8 14 9 20.0 13 10 23.0 11 She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds, respectively. -Referring to Table 18-4, suppose the supervisor constructs an R chart to see if the variability in collection times is in-control. What is the center line of this R chart?

(Multiple Choice)
4.8/5
(36)

TABLE 18-7 A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes samples of size 5 from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below. Sheet Day 1 2 3 4 5 Mean Range 1 8 10 14 6 5 8.6 9 2 8 13 6 6 10 8.6 7 3 10 12 7 7 9 9.0 5 4 5 9 12 7 10 8.6 7 5 8 3 8 9 10 7.6 7 6 9 7 9 6 9 8.0 3 7 10 10 5 7 6 7.6 5 8 10 9 10 6 5 8.0 5 9 6 10 6 9 9 8.0 4 10 6 9 8 6 8 7.4 3 11 8 5 6 10 10 7.8 5 12 6 4 7 7 12 7.2 8 13 7 5 7 6 9 6.8 4 14 5 8 8 7 6 6.8 3 15 7 12 10 6 10 9.0 6 16 7 11 4 7 8 7.4 7 17 8 4 5 4 7 5.6 4 18 11 4 11 11 10 9.4 7 19 6 10 6 10 10 8.4 4 20 6 12 12 6 8 8.8 6 She also decides that the upper specification limit is 10 blemishes. -Referring to Table 18-7, an R chart is to be constructed for the number of blemishes. One way to create the upper control limit involves multiplying the average of the sample ranges by D4. For this data set, the value of D4 is ______ .

(Short Answer)
4.8/5
(33)

Special or assignable causes of variation are signaled by individual fluctuations or patterns in the data.

(True/False)
4.8/5
(38)

TABLE 18-4 A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below. Hour R 1 18.4 25 2 16.9 27 3 23.0 30 4 21.2 23 5 21.0 24 6 24.0 25 7 19.3 12 8 15.8 14 9 20.0 13 10 23.0 11 She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds, respectively. -Referring to Table 18-4, what is the value of the CPL index?

(Short Answer)
4.8/5
(22)

A process is said to be out of control if

(Multiple Choice)
4.8/5
(27)

The control limits are based on the standard deviation of the process.

(True/False)
4.8/5
(29)

TABLE 18-2 A political pollster randomly selects a sample of 100 voters each day for 8 successive days and asks how many will vote for the incumbent. The pollster wishes to construct a p chart to see if the percentage favoring the incumbent candidate is too erratic. Sample Number Favoring (Day) Incumbent Candidate 1 57 2 57 3 53 4 51 5 55 6 60 7 56 8 59 -Referring to Table 18-2, what is the numerical value of the center line for the p chart?

(Multiple Choice)
4.7/5
(39)

TABLE 18-7 A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes samples of size 5 from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below. Sheet Day 1 2 3 4 5 Mean Range 1 8 10 14 6 5 8.6 9 2 8 13 6 6 10 8.6 7 3 10 12 7 7 9 9.0 5 4 5 9 12 7 10 8.6 7 5 8 3 8 9 10 7.6 7 6 9 7 9 6 9 8.0 3 7 10 10 5 7 6 7.6 5 8 10 9 10 6 5 8.0 5 9 6 10 6 9 9 8.0 4 10 6 9 8 6 8 7.4 3 11 8 5 6 10 10 7.8 5 12 6 4 7 7 12 7.2 8 13 7 5 7 6 9 6.8 4 14 5 8 8 7 6 6.8 3 15 7 12 10 6 10 9.0 6 16 7 11 4 7 8 7.4 7 17 8 4 5 4 7 5.6 4 18 11 4 11 11 10 9.4 7 19 6 10 6 10 10 8.4 4 20 6 12 12 6 8 8.8 6 She also decides that the upper specification limit is 10 blemishes. -Referring to Table 18-7, what is the value of the CPU index?

(Short Answer)
4.8/5
(38)

The R chart is a control chart used to monitor a process mean.

(True/False)
4.8/5
(29)

In the United States, the control limits on a control chart are placed so that they are 3 standard deviations above and below a central line.

(True/False)
4.8/5
(41)

CPL >1 implies that the process mean is more than 3 standard deviation away from the lower specification limit.

(True/False)
4.8/5
(36)

TABLE 18-9 The manufacturer of cat food constructed control charts and analyzed several quality characteristics. One characteristic of interest is the weight of the filled cans. The lower specification limit for weight is 2.95 pounds. The table below provides the range and mean of the weights of five cans tested every fifteen minutes during a day's production. Number XBar Range Number XBar Range 1 3.05072 0.0215 16 3.04646 0.073 2 3.01228 0.087 17 3.03868 0.0696 3 3.03558 0.0851 18 3.03338 0.0329 4 3.01014 0.0674 19 3.03322 0.0455 5 3.00858 0.0983 20 3.05078 0.0215 6 3.02704 0.0527 21 3.04808 0.0396 7 3.04268 0.0508 22 3.05348 0.0581 8 3.01052 0.0791 23 3.05516 0.0682 9 3.03464 0.0663 24 3.03426 0.0325 10 3.02034 0.0538 25 3.0516 0.0641 11 3.03764 0.0584 26 3.05562 0.0809 12 3.0409 0.0434 27 3.04402 0.0374 13 3.0519 0.0762 28 3.06458 0.0284 14 3.03994 0.0833 29 3.0544 0.0738 15 3.03788 0.0601 -Referring to Table 18-9, an R chart is to be constructed for the weight. One way to create the lower control limit involves multiplying the average of the sample ranges by D3. For this data set, the value of D3 is _____ .

(Short Answer)
4.9/5
(30)

TABLE 18-6 The maker of a packaged candy wants to evaluate the quality of her production process. On each of 16 consecutive days, she samples 600 bags of candy and determines the number in each day's sample that she considers to be of poor quality. The data that she developed follows. Day Number Poor Proportion Poor 1 33 0.0550000 2 29 0.0483333 3 31 0.0516667 4 32 0.0533333 5 43 0.0716667 6 45 0.0750000 7 46 0.0766667 8 48 0.0500000 9 48 0.0500000 10 46 0.0766667 11 28 0.0466667 12 32 0.0533333 13 28 0.0466667 14 32 0.0533333 15 31 0.0516667 16 24 0.0400000 -Referring to Table 18-6, construct a p control chart for these data.

(Essay)
4.8/5
(40)

TABLE 18-8 Recently, a university switched to a new type of computer-based registration. The registrar is concerned with the amount of time students are spending on the computer registering under the new system. She decides to randomly select 8 students on each of the 12 days of the registration and determine the time each spends on the computer registering. The range, mean, and standard deviation of the times required to register are in the table that follows. Day Range Mean Std.Dev. 1 10 5.250 3.4949 2 31 15.250 10.3060 3 13 20.375 4.9262 4 21 22.875 8.3911 5 35 8.500 11.3767 6 18 7.875 6.9372 7 25 11.250 8.5815 8 30 7.875 9.5235 9 17 10.250 6.3640 10 22 9.500 7.8740 11 27 7.875 8.7086 12 26 12.875 9.3723 -Referring to Table 18-8, an R chart is to be constructed for the time required to register. One way to create the upper control limit involves multiplying the average of the sample ranges by D4. For this data set, the value of D4 is______ .

(Short Answer)
4.9/5
(30)

________causes of variation are correctable without modifying the system.

(Short Answer)
4.9/5
(33)

The Shewhart-Deming cycle plays an important role in which of the following Deming's 14 points for management?

(Multiple Choice)
4.8/5
(23)

TABLE 18-3 A quality control analyst for a light bulb manufacturer is concerned that the time it takes to produce a batch of light bulbs is too erratic. Accordingly, the analyst randomly surveys 10 production periods each day for 14 days and records the sample mean and range for each day. Day (in minutes) 1 58.5 5.1 2 47.6 7.8 3 64.3 6.1 4 60.6 5.7 5 63.7 6.2 6 57.5 6.0 7 55.0 5.4 8 54.9 6.1 9 55.0 5.9 10 62.7 5.0 11 61.9 7.1 12 60.0 6.5 13 58.3 5.9 14 52.0 5.2 -Referring to Table 18-3, suppose the analyst constructs an Xˉ\bar{X} chart to see if the production process is in-control. What is the lower control limit (LCL) for this chart?

(Multiple Choice)
4.8/5
(32)

TABLE 18-8 Recently, a university switched to a new type of computer-based registration. The registrar is concerned with the amount of time students are spending on the computer registering under the new system. She decides to randomly select 8 students on each of the 12 days of the registration and determine the time each spends on the computer registering. The range, mean, and standard deviation of the times required to register are in the table that follows. Day Range Mean Std.Dev. 1 10 5.250 3.4949 2 31 15.250 10.3060 3 13 20.375 4.9262 4 21 22.875 8.3911 5 35 8.500 11.3767 6 18 7.875 6.9372 7 25 11.250 8.5815 8 30 7.875 9.5235 9 17 10.250 6.3640 10 22 9.500 7.8740 11 27 7.875 8.7086 12 26 12.875 9.3723 -Referring to Table 18-8, an R chart is to be constructed for the time required to register. One way to create the lower control limit involves multiplying the average of the sample ranges by D3. For this data set, the value of D3 is _____ .

(Short Answer)
4.9/5
(31)

TABLE 18-3 A quality control analyst for a light bulb manufacturer is concerned that the time it takes to produce a batch of light bulbs is too erratic. Accordingly, the analyst randomly surveys 10 production periods each day for 14 days and records the sample mean and range for each day. Day (in minutes) R 1 58.5 5.1 2 47.6 7.8 3 64.3 6.1 4 60.6 5.7 5 63.7 6.2 6 57.5 6.0 7 55.0 5.4 8 54.9 6.1 9 55.0 5.9 10 62.7 5.0 11 61.9 7.1 12 60.0 6.5 13 58.3 5.9 14 52.0 5.2 -Referring to Table 18-3, suppose the analyst constructs an Xˉ\bar{X} chart to see if the production process is in-control. What is the upper control limit (UCL) for this chart?

(Multiple Choice)
4.7/5
(41)
Showing 41 - 60 of 113