Exam 23: Cost Estimation and Cost Behaviour

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

English Ltd. analyzed the relationship between total factory overhead and changes in direct labour hours. It found the following: Y = £6,000 + £6X The Y in the equation is an estimate of

(Multiple Choice)
4.9/5
(32)

What is the difference between a correlation equal to -1 and a correlation equal to 0?

(Multiple Choice)
4.8/5
(40)

The scatterplot method of cost estimation

(Multiple Choice)
4.9/5
(31)

Figure 23-3 Abboud Company is planning to introduce a new product with an 80 percent cumulative learning curve for production for batches of 1,000 units. The variable labour costs are £30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are £10,000 in fixed costs not subject to learning. -Refer to Figure 23-3. What is the individual unit time (labour hours) to produce 2,000 units?

(Multiple Choice)
4.8/5
(46)

In the formula Y = a + bx, a refers to the

(Multiple Choice)
4.9/5
(38)

The percentage change in the dependent variable that is explained by the change in the independent variable is measured by the

(Multiple Choice)
4.7/5
(37)

The following computer printout estimated overhead costs using multiple regression: The following computer printout estimated overhead costs using multiple regression:   Which slope and intercept parameters are significant at the 0.05 level? Which slope and intercept parameters are significant at the 0.05 level?

(Multiple Choice)
4.8/5
(38)

Kane Ltd. found its maintenance cost and sales revenues to be somewhat correlated. Last year's high and low observations were as follows: Kane Ltd. found its maintenance cost and sales revenues to be somewhat correlated. Last year's high and low observations were as follows:   What is the fixed portion of the maintenance cost? What is the fixed portion of the maintenance cost?

(Multiple Choice)
4.8/5
(42)

In the formula Y = a + bx, x refers to the

(Multiple Choice)
4.8/5
(43)

Which of the following is a strength of the high-low advantage method?

(Multiple Choice)
4.7/5
(28)

Greene Enterprises has the following information about its truck fleet miles and operating costs: Greene Enterprises has the following information about its truck fleet miles and operating costs:   What is the best estimate of total costs using the high-low method if the expected fleet mileage for 2008 is 500,000 miles? What is the best estimate of total costs using the high-low method if the expected fleet mileage for 2008 is 500,000 miles?

(Multiple Choice)
4.9/5
(40)

Advantages of the method of least squares over the high-low method include all the following EXCEPT

(Multiple Choice)
4.7/5
(37)

Innova, SA., is beginning the production of a new product. Management believes that 500 labour hours will be required to complete the new unit. A 90 percent cumulative average-time learning curve model for direct labour hours is assumed to be valid. Data on costs are as follows: Innova, SA., is beginning the production of a new product. Management believes that 500 labour hours will be required to complete the new unit. A 90 percent cumulative average-time learning curve model for direct labour hours is assumed to be valid. Data on costs are as follows:   Required:  a. Set up a table with columns for cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours using the cumulative average-time learning curve. Complete the table for 1, 2, 4, and 8 units. b. Set up a similar table assuming an 80 percent with the cumulative average-time learning curve. c. What is the difference in variable cost of producing four units? Required: a. Set up a table with columns for cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours using the cumulative average-time learning curve. Complete the table for 1, 2, 4, and 8 units. b. Set up a similar table assuming an 80 percent with the cumulative average-time learning curve. c. What is the difference in variable cost of producing four units?

(Essay)
4.9/5
(34)

The following information was available about supplies cost for the first three months of the year: The following information was available about supplies cost for the first three months of the year:   Using the high-low method, an estimate of supplies cost at 4,500 units of production would be Using the high-low method, an estimate of supplies cost at 4,500 units of production would be

(Multiple Choice)
4.9/5
(48)

SeyChy collected the following data on manufacturing costs and activity cost drivers for two months: SeyChy collected the following data on manufacturing costs and activity cost drivers for two months:   Required:  Required: SeyChy collected the following data on manufacturing costs and activity cost drivers for two months:   Required:

(Essay)
4.9/5
(42)

In a simple least-squares regression where X refers to the number of sales calls made by a sales department and Y refers to the monthly total cost of the sales department, the R-squared in the regression output would represent:

(Multiple Choice)
4.9/5
(38)

In the formula Y = a + bx, b refers to the

(Multiple Choice)
5.0/5
(32)

The following computer printout estimated overhead costs using multiple regression: The following computer printout estimated overhead costs using multiple regression:   The model being measured is The model being measured is

(Multiple Choice)
4.8/5
(30)

Figure 23-1 Lee Ltd. manufactures and sells party items. The following representative direct labour hours and production costs are provided for a four-month period:  Figure 23-1 Lee Ltd. manufactures and sells party items. The following representative direct labour hours and production costs are provided for a four-month period:   Let a = Fixed production costs per month b = Variable production costs per direct labour hour n = Number of months X = Direct labour hours per month Y = Total monthly production costs  \Sigma  = Summation -Refer to Figure 23-1. The cost function derived by the least-squares cost estimation method Let a = Fixed production costs per month b = Variable production costs per direct labour hour n = Number of months X = Direct labour hours per month Y = Total monthly production costs Σ\Sigma = Summation -Refer to Figure 23-1. The cost function derived by the least-squares cost estimation method

(Multiple Choice)
4.9/5
(38)

In the formula Y = a + bx, Y refers to the

(Multiple Choice)
4.7/5
(46)
Showing 41 - 60 of 63
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)