Exam 8: The Mathematics of Scheduling: Chasing the Critical Path

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A project consists of six tasks labeled A through F. The table shown below gives the processing times and precedence relations for the tasks. Construct the project digraph. A project consists of six tasks labeled A through F. The table shown below gives the processing times and precedence relations for the tasks. Construct the project digraph.   -Consider the project shown above;  use the priority list A, B, C, D, E, F to find the project finish time fin using N = 2 processors. -Consider the project shown above; use the priority list A, B, C, D, E, F to find the project finish time fin using N = 2 processors.

(Short Answer)
4.9/5
(35)

  -Consider the project from problem 6; use the priority list A, B, C, D, E, F to find the project finish time fin using N = 2 processors. -Consider the project from problem 6; use the priority list A, B, C, D, E, F to find the project finish time fin using N = 2 processors.

(Short Answer)
4.8/5
(49)

Consider the project digraph shown below; what is the critical time for vertex D?

(Multiple Choice)
4.9/5
(36)

A project consists of six tasks labeled A through F . The table shown below gives the processing times and precedence relations for these tasks. Construct the project digraph. A project consists of six tasks labeled  A  through  F .  The table shown below gives the processing times and precedence relations for these tasks. Construct the project digraph.

(Essay)
4.8/5
(36)

Which of the digraphs below have an arc set of A = {GH, GO, GT, HO, HT, TO, OS}? Which of the digraphs below have an arc set of A = {GH, GO, GT, HO, HT, TO, OS}?

(Multiple Choice)
5.0/5
(36)

A project consists of seven tasks labeled A through G. The table shown below gives the processing times and precedence relations. Which project digraph represents this situation? A project consists of seven tasks labeled A through G. The table shown below gives the processing times and precedence relations. Which project digraph represents this situation?   -Consider the project shown above ; use the priority list B, D, F, E, A, G, C to find the project finish time fin using N = 3 processors. -Consider the project shown above ; use the priority list B, D, F, E, A, G, C to find the project finish time fin using N = 3 processors.

(Multiple Choice)
4.9/5
(34)

  -Consider the digraph shown above ; which vertices, if any, are incident to I? -Consider the digraph shown above ; which vertices, if any, are incident to I?

(Short Answer)
4.9/5
(33)

Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 2 processors. Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 2 processors.

(Short Answer)
4.8/5
(38)

  -Consider the digraph shown above ; what is the outdegree of vertex A? -Consider the digraph shown above ; what is the outdegree of vertex A?

(Short Answer)
4.8/5
(32)

The catalog at your college gives the following information regarding math classes. A prerequisite for Calculus III is Calculus II. A prerequisite for Calculus II is Calculus I. Linear Algebra can only be taken after both Calculus II and Fundamentals of Mathematical Proofs have been taken. A prerequisite for Fundamentals of Mathematical Proofs is Calculus I. In order to take Real Analysis I, a student must have completed Calculus III and Linear Algebra. A prerequisite for Real Analysis II is Real Analysis I. Draw a digraph which models the relationships between the math classes Calculus I, Calculus II, Calculus III, Fundamentals of Mathematical Proofs, Linear Algebra, Real Analysis I, and Real Analysis II.

(Essay)
4.8/5
(41)

  -Consider the digraphs shown above ; how many vertices from the digraph shown in figure 2 are incident to vertex O? -Consider the digraphs shown above ; how many vertices from the digraph shown in figure 2 are incident to vertex O?

(Multiple Choice)
4.9/5
(43)

  -Consider the digraph shown above ; which vertices, if any, are incident to E? -Consider the digraph shown above ; which vertices, if any, are incident to E?

(Short Answer)
4.8/5
(33)

Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N=2 processors. Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using  N=2  processors.

(Multiple Choice)
4.9/5
(37)

A project consists of six tasks labeled A through F. The table shown below gives the processing times and precedence relations for the tasks. Construct the project digraph. A project consists of six tasks labeled A through F. The table shown below gives the processing times and precedence relations for the tasks. Construct the project digraph.

(Essay)
4.8/5
(37)

Consider the project digraph shown below; apply the critical-path algorithm to find the project finish time fin using N = 2 processors.

(Multiple Choice)
4.9/5
(38)

Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 2 processors. Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 2 processors.

(Short Answer)
4.8/5
(30)

  -Consider the digraphs shown above ; which of the digraphs have an outdegree of 3 at vertex G? -Consider the digraphs shown above ; which of the digraphs have an outdegree of 3 at vertex G?

(Multiple Choice)
4.8/5
(35)

  -Consider the project digraph shown above; apply the critical-path algorithm to find the project finish time fin using N = 3 processors. -Consider the project digraph shown above; apply the critical-path algorithm to find the project finish time fin using N = 3 processors.

(Short Answer)
4.9/5
(34)

Consider the project digraph shown below; what is the critical time for vertex A? Consider the project digraph shown below; what is the critical time for vertex A?

(Multiple Choice)
4.9/5
(41)

In a project, which of the following relations is true?

(Multiple Choice)
4.8/5
(38)
Showing 21 - 40 of 40
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)