Exam 8: The Mathematics of Scheduling: Chasing the Critical Path
Exam 1: The Mathematics of Elections: the Paradoxes of Democracy40 Questions
Exam 2: The Mathematics of Power: Weighted Voting40 Questions
Exam 3: The Mathematics of Sharing: Fair-Division Games38 Questions
Exam 4: The Mathematics of Apportionment: Making the Rounds40 Questions
Exam 5: The Mathematics of Getting Around: Euler Paths and Circuits37 Questions
Exam 6: The Mathematics of Touring: Traveling Salesman Problems40 Questions
Exam 7: The Cost of Being Connected40 Questions
Exam 8: The Mathematics of Scheduling: Chasing the Critical Path40 Questions
Exam 9: Population Growth Models: There Is Strength in Numbers40 Questions
Exam 10: Financial Mathematics: Money Matters40 Questions
Exam 11: The Mathematics of Symmetry: Beyond Reflection40 Questions
Exam 12: Fractal Geometry: the Kinky Nature of Nature39 Questions
Exam 13: Fibonacci Numbers and the Golden Ratio: Tales of Rabbits and Gnomons40 Questions
Exam 14: Censuses, Surveys, Polls, and Studies: the Joys of Collecting Data40 Questions
Exam 15: Graphs, Charts, and Numbers: the Data Show and Tell40 Questions
Exam 16: Probabilities, Odds, and Expectations: Measuring Uncertainty and Risk40 Questions
Exam 17: The Mathematics of Normality: the Call of the Bell40 Questions
Select questions type
A project consists of six tasks labeled A through F. The table shown below gives the processing times and precedence relations for the tasks. Construct the project digraph.
-Consider the project shown above; use the priority list A, B, C, D, E, F to find the project finish time fin using N = 2 processors.

(Short Answer)
4.9/5
(35)
-Consider the project from problem 6; use the priority list A, B, C, D, E, F to find the project finish time
fin using N = 2 processors.

(Short Answer)
4.8/5
(49)
Consider the project digraph shown below; what is the critical time for vertex D?
(Multiple Choice)
4.9/5
(36)
A project consists of six tasks labeled A through F . The table shown below gives the processing times and precedence relations for these tasks. Construct the project digraph.


(Essay)
4.8/5
(36)
Which of the digraphs below have an arc set of A = {GH, GO, GT, HO, HT, TO, OS}?

(Multiple Choice)
5.0/5
(36)
A project consists of seven tasks labeled A through G. The table shown below gives the processing times and precedence relations. Which project digraph represents this situation?
-Consider the project shown above ; use the priority list B, D, F, E, A, G, C to find the project finish time fin using N = 3 processors.

(Multiple Choice)
4.9/5
(34)
-Consider the digraph shown above ; which vertices, if any, are incident to I?

(Short Answer)
4.9/5
(33)
Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 2 processors.

(Short Answer)
4.8/5
(38)
-Consider the digraph shown above ; what is the outdegree of vertex A?

(Short Answer)
4.8/5
(32)
The catalog at your college gives the following information regarding math classes.
A prerequisite for Calculus III is Calculus II. A prerequisite for Calculus II is Calculus I. Linear Algebra can only be taken after both Calculus II and Fundamentals of Mathematical Proofs have been taken. A prerequisite for Fundamentals of Mathematical Proofs is Calculus I. In order to take Real Analysis I, a student must have completed Calculus III and Linear Algebra. A prerequisite for Real Analysis II is Real
Analysis I.
Draw a digraph which models the relationships between the math classes Calculus I, Calculus II,
Calculus III, Fundamentals of Mathematical Proofs, Linear Algebra, Real Analysis I, and Real
Analysis II.
(Essay)
4.8/5
(41)
-Consider the digraphs shown above ; how many vertices from the digraph shown in figure 2 are incident to vertex O?

(Multiple Choice)
4.9/5
(43)
-Consider the digraph shown above ; which vertices, if any, are incident to E?

(Short Answer)
4.8/5
(33)
Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N=2 processors.


(Multiple Choice)
4.9/5
(37)
A project consists of six tasks labeled A through F. The table shown below gives the processing times and precedence relations for the tasks. Construct the project digraph.


(Essay)
4.8/5
(37)
Consider the project digraph shown below; apply the critical-path algorithm to find the project finish time fin using N = 2 processors.
(Multiple Choice)
4.9/5
(38)
Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 2 processors. 

(Short Answer)
4.8/5
(30)
-Consider the digraphs shown above ; which of the digraphs have an outdegree of 3 at vertex G?

(Multiple Choice)
4.8/5
(35)
-Consider the project digraph shown above; apply the critical-path algorithm to find the project finish time fin using N = 3 processors.

(Short Answer)
4.9/5
(34)
Consider the project digraph shown below; what is the critical time for vertex A?

(Multiple Choice)
4.9/5
(41)
Showing 21 - 40 of 40
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)