Exam 8: The Mathematics of Scheduling: Chasing the Critical Path
Exam 1: The Mathematics of Elections: the Paradoxes of Democracy40 Questions
Exam 2: The Mathematics of Power: Weighted Voting40 Questions
Exam 3: The Mathematics of Sharing: Fair-Division Games38 Questions
Exam 4: The Mathematics of Apportionment: Making the Rounds40 Questions
Exam 5: The Mathematics of Getting Around: Euler Paths and Circuits37 Questions
Exam 6: The Mathematics of Touring: Traveling Salesman Problems40 Questions
Exam 7: The Cost of Being Connected40 Questions
Exam 8: The Mathematics of Scheduling: Chasing the Critical Path40 Questions
Exam 9: Population Growth Models: There Is Strength in Numbers40 Questions
Exam 10: Financial Mathematics: Money Matters40 Questions
Exam 11: The Mathematics of Symmetry: Beyond Reflection40 Questions
Exam 12: Fractal Geometry: the Kinky Nature of Nature39 Questions
Exam 13: Fibonacci Numbers and the Golden Ratio: Tales of Rabbits and Gnomons40 Questions
Exam 14: Censuses, Surveys, Polls, and Studies: the Joys of Collecting Data40 Questions
Exam 15: Graphs, Charts, and Numbers: the Data Show and Tell40 Questions
Exam 16: Probabilities, Odds, and Expectations: Measuring Uncertainty and Risk40 Questions
Exam 17: The Mathematics of Normality: the Call of the Bell40 Questions
Select questions type
Suppose that you work at a local convenience store. The store has just closed and you and three other co-workers must complete a list of tasks before any of you can leave for the night. Each task may only be worked on by one person. What is the optimal amount of time that it will take to complete the list of tasks knowing that all tasks are independent from one another?
(a) 18
(b) 22
(c)25
(d)27
(e)None of the

Free
(Short Answer)
4.8/5
(30)
Correct Answer:
B
Suppose that you work at a local convenience store. The store has just closed and you and one other co-worker must complete a list of tasks before any of you can leave for the night. Each task may only be worked on by one person. What is the optimal amount of time that it will take to complete the list of tasks knowing that all tasks are independent from one another?


Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
B
A project consists of seven tasks labeled A through G . The table shown below gives the processing times and precedence relations. Which project digraph represents this situation?


Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
C
-Consider the digraphs shown above ; which of the digraphs have an outdegree of 3 at vertex O?

(Multiple Choice)
4.9/5
(36)
A project consists of seven tasks labeled A through G . The table shown below gives the processing times and precedence relations. Which project digraph represents this situation?
-Consider the project above; use the priority list A, C, B, F, G, D, E to find the project finish time fin using N = 3 processors.

(Multiple Choice)
4.8/5
(34)
Consider the project digraph shown below; apply the critical-path algorithm to find the project finish time f i n using N=2 processors.


(Multiple Choice)
4.9/5
(33)
Suppose that you work at a local convenience store. The store has just closed and you and two other co-workers must complete a list of tasks before any of you can leave for the night. Each task may only be worked on by one person. What is the optimal amount of time that it will take to complete the list of tasks knowing that all tasks are independent from one another? 

(Short Answer)
4.8/5
(33)
-Consider the digraphs shown above ; how many arcs from the digraph shown in figure 2 are adjacent to arc HT?

(Multiple Choice)
4.7/5
(31)
-Consider the digraph shown above ; which arcs, if any, are adjacent to BO?

(Short Answer)
4.9/5
(35)
A project consists of seven tasks labeled A through G. The table shown below gives the processing times and precedence relations. Which project digraph represents this situation?

(Multiple Choice)
4.9/5
(35)
Consider the digraph with vertex set V = {I, C, H, A, B, O, D} and arc set A = {IC, ID, CH, HA, HO, AI, AB, BO, BD, OD}. Draw the digraph.
(Essay)
4.9/5
(33)
Consider the project digraph shown below; you plan on applying the critical-path algorithm to complete the project. However, you have a choice of using either N = 2 processors or N = 3 processors. Is it more efficient to use three processors as opposed to two? Explain. 

(Essay)
4.8/5
(35)
Suppose that you work at a local convenience store. The store has just closed and you and one other co-worker must complete a list of tasks before any of you can leave for the night. Each task may only be worked on by one person. What is the optimal amount of time that it will take to complete the list of tasks knowing that all tasks are independent from one another? Hint: You are guaranteed that a
project finish time is optimal if there is zero idle time. 

(Short Answer)
4.8/5
(38)
-Consider the digraph shown above ; what is the indegree of vertex B?

(Short Answer)
4.9/5
(31)
-Consider the digraph shown above ; which arcs, if any, are adjacent to AD?

(Short Answer)
4.8/5
(40)
In a specific project, the addition of more processors will always cause the optimal time to decrease.
(Multiple Choice)
4.7/5
(32)
Which of the digraphs below have arc OS as part of its arc set?


(Multiple Choice)
4.8/5
(29)
Consider the project digraph shown below; apply the decreasing-time algorithm to find the project finish time fin using N = 3 processors. 

(Short Answer)
4.8/5
(42)
-Consider the project digraph from problem 8; apply the critical-path algorithm to find the project finish time fin using N = 2 processors.

(Short Answer)
4.9/5
(33)
Showing 1 - 20 of 40
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)