For an activity in a CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is ?

(Multiple Choice)
4.8/5
(30)

The critical path in a CPM analysis is found by locating the activities times with zero slack.

(True/False)
4.8/5
(34)

The second step in managing a project is writing the Statement of Work.

(True/False)
4.8/5
(51)

Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.   If you crash this project to reduce the total time by four days, what is the total time of the project and total cost? If you crash this project to reduce the total time by four days, what is the total time of the project and total cost?

(Multiple Choice)
4.8/5
(39)

A project starts out as which of the following?

(Multiple Choice)
4.7/5
(39)

A simple project listing of five activities and their respective time estimates are presented below: A simple project listing of five activities and their respective time estimates are presented below:   Using CPM, which activities make up the critical path? Using CPM, which activities make up the critical path?

(Multiple Choice)
4.8/5
(45)

The fact that organizations are flattening is one of the reasons that project management is important.

(True/False)
4.8/5
(40)

A work breakdown structure is used in project management but it is not used when the critical path method is involved.

(True/False)
4.9/5
(38)

Using the Time-Cost CPM model, the crash time is the shortest possible time allowed for each activity in the project.

(True/False)
4.8/5
(32)

A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below: A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below:   Using CPM, which activities make up the critical path? Using CPM, which activities make up the critical path?

(Multiple Choice)
4.9/5
(41)