Exam 6: Allocating Resources to the Project
Exam 1: The World of Project Management97 Questions
Exam 2: The Manager, the Organization, and the Team93 Questions
Exam 3: Planning the Project85 Questions
Exam 4: Budgeting the Project69 Questions
Exam 5: Scheduling the Project108 Questions
Exam 6: Allocating Resources to the Project89 Questions
Exam 7: Monitoring and Controlling the Project96 Questions
Exam 8: Evaluating and Terminating the Project80 Questions
Select questions type
One limitation of Microsoft Project is that all resources must share the same availability calendar.
(True/False)
4.7/5
(32)
Crashing non-critical activities will influence project duration.
(True/False)
4.8/5
(25)
Task duration is not necessarily dictated by the amount of labor required to complete the task.
(True/False)
4.7/5
(36)
A task's duration is a function of both the amount of labor required to complete the task as well as the cost required to complete it.
(True/False)
4.8/5
(32)
Mark, the chief editor of a magazine, needs to create a list of all the in-house writers, designers, and freelancers who will be working on the next issue of the magazine. He also needs to list their activities, their schedules, and their cost per hour. In the context of project management, which of the following should Mark use to create this list?
(Multiple Choice)
4.8/5
(32)
Pools of like resources from which labor can be added temporarily to projects raise the cost of managing the project.
(True/False)
4.9/5
(36)
Vanessa, a student, has to submit two assignments, A and B, on the same day. Each assignment is divided into three tasks. She has to write the first draft, check it for accuracy, and let her friend review it before submission. Each of these tasks takes 5 hours. In order to multitask effectively, Vanessa should:
(Multiple Choice)
4.8/5
(33)
The safety time added to chains other than the critical chain is called…
(Multiple Choice)
4.9/5
(34)
Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.
(True/False)
5.0/5
(31)
The following describes which priority rule: With this rule, the greater the use of a specific resource on a task, the higher the task's priority for the resource.
(Multiple Choice)
4.8/5
(31)
All of the following are criteria available to help choose the priority rule mentioned in the textbook except;
(Multiple Choice)
4.9/5
(33)
When crashing a task, the usual assumption is that a task is crashed the full amount or none at all.
(True/False)
4.9/5
(28)
When the work is routine, fast-tracking rarely causes serious problems.
(True/False)
4.7/5
(31)
The following describes which priority rule: Activities are scheduled to start on their earliest start times (ES), and resources are made available with that in mind.
(Multiple Choice)
4.8/5
(27)
The following describes which priority rule: This rule maximizes the number of tasks that can be completed by a system in a given time period.
(Multiple Choice)
4.8/5
(25)
It is considered good management to crash the least costly activities before the more costly ones.
(True/False)
4.7/5
(36)
Trade-offs must be made in order to optimize the use of limited resources.
(True/False)
4.8/5
(36)
Showing 21 - 40 of 89
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)