Exam 5: Scheduling the Project

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Before this can be achieved or realized, all its predecessor activities must be completed.

(Multiple Choice)
4.8/5
(40)

If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.

(True/False)
4.7/5
(35)

Formula for the expected completion time of an activity.

(Multiple Choice)
4.9/5
(33)

Why is it necessary for the project manager (PM) to be aware and to manage the slack in the project?

(Essay)
4.8/5
(33)

"Merger" is a term used to describe the situation in which two or more paths in a network join together.

(True/False)
4.8/5
(29)

A Gantt chart cannot depict a critical path, only a PERT/CPM chart can.

(True/False)
4.9/5
(32)

An activity using slack does not impact any other activity.

(True/False)
4.9/5
(24)

The amount of time a noncritical task can be delayed without delaying the project is called?

(Multiple Choice)
4.9/5
(39)

High velocity is a goal of Agile scheduling.

(True/False)
4.7/5
(32)

A Term not used in the discussion of PERT/CPM analysis is

(Multiple Choice)
4.8/5
(31)

An approximation of the variance for an activity.

(Multiple Choice)
5.0/5
(38)

The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.

(True/False)
4.9/5
(40)

A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a dummy task.

(True/False)
4.8/5
(32)

All project-related statistical calculations are performed using the normal distribution.

(True/False)
4.8/5
(33)

An event is a series of connected activities.

(True/False)
4.9/5
(27)

The cost to complete an activity is always known in advance.

(True/False)
4.8/5
(42)

Explain why the term critical path has less meaning in cases where the activity times are not known with certainty.

(Essay)
4.7/5
(29)

The shortest time to complete a network is equal to the duration of the longest path through the network.

(True/False)
4.9/5
(34)

Float refers to the amount of time a noncritical task can be delayed without causing a delay in the entire project.

(True/False)
4.8/5
(32)

Which type of following precedence diagramming convention is the most common?

(Multiple Choice)
4.8/5
(39)
Showing 81 - 100 of 108