Nessage Mique, a niche fashion boutique, displays its production process by using a network of nodes and arrows. The nodes are used to depict the state of completion of various activities and the arrows are used to depict their order of precedence. Which of the following project networks is Nessage Mique using in the given scenario?
(Multiple Choice)
4.7/5
(33)
Which type of precedence diagramming convention is the following: Activity 5 cannot begin until Activity 4 has been underway for at least 2 days.
(Multiple Choice)
4.9/5
(30)
The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.
(True/False)
4.7/5
(31)