Exam 38: Network Planning and Analysis
Exam 1: Introduction to Business Mathematics and Statistics10 Questions
Exam 2: Sampling and Data Collection10 Questions
Exam 3: Data and Their Accuracy10 Questions
Exam 4: Frequency Distributions and Charts10 Questions
Exam 5: General Charts and Graphs10 Questions
Exam 6: Arithmetic Mean10 Questions
Exam 7: Median10 Questions
Exam 8: Mode and Other Measures of Location10 Questions
Exam 9: Measures of Dispersion and Skewness10 Questions
Exam 10: Standard Deviation10 Questions
Exam 11: Quantiles and the Quartile Deviation10 Questions
Exam 12: Linear Functions and Graphs10 Questions
Exam 13: Regression Techniques10 Questions
Exam 14: Correlation Techniques10 Questions
Exam 15: Time Series Model10 Questions
Exam 16: Time Series Trend10 Questions
Exam 17: Seasonal Variation and Forecasting10 Questions
Exam 18: Index Relatives10 Questions
Exam 19: Composite Index Numbers10 Questions
Exam 20: Special Published Indices10 Questions
Exam 21: Interest and Depreciation10 Questions
Exam 22: Present Value and Investment Appraisal10 Questions
Exam 23: Annuities10 Questions
Exam 24: Functions and Graphs10 Questions
Exam 25: Linear Equations10 Questions
Exam 26: Quadratic and Cubic Equations10 Questions
Exam 27: Differentiation and Integration10 Questions
Exam 28: Cost, Revenue and Profit Functions10 Questions
Exam 29: Set Theory and Enumeration10 Questions
Exam 30: Introduction to Probability9 Questions
Exam 31: Conditional Probability and Expectation9 Questions
Exam 32: Combinations and Permutations10 Questions
Exam 33: Binomial and Poisson Distributions10 Questions
Exam 34: Normal Distribution10 Questions
Exam 35: Linear Inequalities10 Questions
Exam 36: Matrices10 Questions
Exam 37: Inventory Control10 Questions
Exam 38: Network Planning and Analysis10 Questions
Select questions type
Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start? 

Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
B
Which of the following statements concerning events and activities is NOT true?
Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
D
Consider the following network diagram [insert network diagram from top of p555]. Which of the following statements is TRUE?
(Multiple Choice)
4.9/5
(42)
Which of the following options is the BEST definition of a critical path?
(Multiple Choice)
4.8/5
(37)
Which of the following options is the BEST definition of network planning?
(Multiple Choice)
4.9/5
(36)
What is the basic process for calculating the event late time for an event in the middle of a network diagram?
(Multiple Choice)
4.8/5
(37)