Exam 38: Network Planning and Analysis

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start? Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start?

Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
Verified

B

What is a precedence table?

Free
(Multiple Choice)
4.7/5
(42)
Correct Answer:
Verified

A

Which of the following statements concerning events and activities is NOT true?

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
Verified

D

How might the earliest activity finish time be calculated?

(Multiple Choice)
4.8/5
(46)

Which of the following statements about float is NOT true?

(Multiple Choice)
4.7/5
(50)

Consider the following network diagram [insert network diagram from top of p555]. Which of the following statements is TRUE?

(Multiple Choice)
4.9/5
(42)

Which of the following options is the BEST definition of a critical path?

(Multiple Choice)
4.8/5
(37)

Which of the following options is the BEST definition of network planning?

(Multiple Choice)
4.9/5
(36)

Which statement concerning dummy activities is NOT true?

(Multiple Choice)
4.9/5
(40)

What is the basic process for calculating the event late time for an event in the middle of a network diagram?

(Multiple Choice)
4.8/5
(37)