Exam 4: PRINCE2 Foundation (PRF)
Exam 1: ASTQB Certified Mobile Tester70 Questions
Exam 2: BCS Foundation Certificate in Business Analysis (BH0-013)142 Questions
Exam 3: ISTQB-ISEB Certified Tester Foundation Level (BH0-010)98 Questions
Exam 4: PRINCE2 Foundation (PRF)141 Questions
Exam 5: BCS Practitioner Certificate in Requirements Engineering 201830 Questions
Exam 6: ISTQB-BCS Certified Tester Advanced Level- Test Manager (2012)63 Questions
Exam 7: BCS Foundation Certificate in User Experience8 Questions
Select questions type
In which product would you find a product's quality tolerance defined?
(Multiple Choice)
4.7/5
(38)
When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
(Multiple Choice)
4.7/5
(37)
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
(Multiple Choice)
4.9/5
(38)
Which is NOT confirmed during the Initiating a Project process?
(Multiple Choice)
4.8/5
(39)
Which of the following are objectives of the Directing a Project process? 1. Ensure corporate or programme management has an interface to a project 2. Ensure that work on products allocated to a team is authorized 3. Ensure there is authority to initiate a project 4. Ensure that a project remains viable
(Multiple Choice)
4.8/5
(45)
Which product documents the information needed to demonstrate continued business justification?
(Multiple Choice)
4.7/5
(37)
If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?
(Multiple Choice)
4.9/5
(40)
Which is one of the six aspects of project performance that needs to be managed?
(Multiple Choice)
4.8/5
(34)
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
(Multiple Choice)
4.8/5
(42)
Which process is used by a Team Manager to coordinate work on one or more of the project's products?
(Multiple Choice)
4.9/5
(40)
Which risk response type is a recommended response to both an opportunity and a threat?
(Multiple Choice)
4.9/5
(39)
Where should a Team Manager look for information on the quality required for a product?
(Multiple Choice)
4.9/5
(45)
Identify the missing words in the following sentence. The Team Manager should check the [ ? ] for any interfaces that must be maintained while developing products.
(Multiple Choice)
4.8/5
(39)
Which of the following are typical core activities within configuration management? 1. Planning 2. Risk assessment 3. Verification and audit 4. Identification
(Multiple Choice)
4.9/5
(38)
Showing 101 - 120 of 141
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)