Exam 4: PRINCE2 Foundation (PRF)
Exam 1: ASTQB Certified Mobile Tester70 Questions
Exam 2: BCS Foundation Certificate in Business Analysis (BH0-013)142 Questions
Exam 3: ISTQB-ISEB Certified Tester Foundation Level (BH0-010)98 Questions
Exam 4: PRINCE2 Foundation (PRF)141 Questions
Exam 5: BCS Practitioner Certificate in Requirements Engineering 201830 Questions
Exam 6: ISTQB-BCS Certified Tester Advanced Level- Test Manager (2012)63 Questions
Exam 7: BCS Foundation Certificate in User Experience8 Questions
Select questions type
Which role is responsible for the management of a risk assigned to it?
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
B
Which principle helps to define what should be included and what should be excluded from a project?
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
B
Which is a purpose of the Managing Product Delivery process?
Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
B
Which is a difference between management and technical stages?
(Multiple Choice)
4.9/5
(37)
Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?
(Multiple Choice)
4.7/5
(34)
Which is a purpose of the Managing a Stage Boundary process?
(Multiple Choice)
4.8/5
(39)
Which of the following statements about the Closing a Project process are true? 1. The Closing a Project process provides a fixed point for the receipt of completed Work 2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
(Multiple Choice)
4.8/5
(27)
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
(Multiple Choice)
4.9/5
(36)
What process provides the information required to decide whether to authorize the delivery of a project?
(Multiple Choice)
5.0/5
(36)
What is the collective name for individuals or groups who may be affected by a project?
(Multiple Choice)
4.9/5
(30)
When should the Project Board refer to corporate or programme management for a decision?
(Multiple Choice)
4.7/5
(27)
Which is NOT a true statement about the Managing a Stage Boundary process?
(Multiple Choice)
4.7/5
(28)
Identify the missing product in the following sentence. When assessing an issue during the Controlling a Stage process, the [ ? ] provides essential information to evaluate the viability of the project.
(Multiple Choice)
4.8/5
(36)
Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?
(Multiple Choice)
4.8/5
(39)
Which theme defines the accountability for realization of the project's benefits?
(Multiple Choice)
4.9/5
(31)
Showing 1 - 20 of 141