Exam 7: Project Cost Management
Exam 1: Introduction to Project Management95 Questions
Exam 2: The Project Management and Information Technology Context85 Questions
Exam 3: The Project Management Process Groups: a Case Study76 Questions
Exam 4: Project Integration Management81 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management80 Questions
Exam 9: Project Human Resource Management84 Questions
Exam 10: Project Communications Management75 Questions
Exam 11: Project Risk Management75 Questions
Exam 12: Project Procurement Management81 Questions
Exam 13: Project Stakeholder Management50 Questions
Select questions type
The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity is known as the _____.
Free
(Short Answer)
4.8/5
(41)
Correct Answer:
rate of performance (RP)
Variances are calculated by subtracting the actual cost from _____.
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
A
_____ are revenues minus expenditures.
Free
(Short Answer)
5.0/5
(36)
Correct Answer:
Profits
A(n) _____ estimate is done very early in a project or even before a project is officially started.
(Short Answer)
4.9/5
(39)
A schedule performance index of one means that the project is on schedule.
(True/False)
4.7/5
(29)
Definitive estimates are made one year or less prior to project completion.
(True/False)
4.9/5
(36)
_____ costing considers the total cost of ownership, or development plus support costs, for a project.
(Short Answer)
4.8/5
(49)
_____ helps develop an accurate projection of a project's financial expenses and benefits.
(Multiple Choice)
4.9/5
(45)
Analogous estimates are the most accurate technique to estimate costs.
(True/False)
4.9/5
(45)
Determining the budget involves allocating the project cost estimate to individual work items over time.
(True/False)
4.8/5
(44)
What are the three basic types of cost estimating? Describe each type.
(Essay)
4.8/5
(41)
Project costs, like project schedules, grow out of the basic documents that initiate a project, like the _____.
(Short Answer)
4.8/5
(35)
Which of the following reserves allows for future situations that are unpredictable?
(Multiple Choice)
4.9/5
(42)
The main goal of the _____ process is to produce a cost baseline for measuring project performance and project funding requirements.
(Multiple Choice)
4.9/5
(35)
Which of the following types of estimate use the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
(Multiple Choice)
5.0/5
(37)
Which of the following is an output of the process of controlling costs?
(Multiple Choice)
5.0/5
(44)
Showing 1 - 20 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)