Q = LFL, LT = 2, SS = 0 Q = LFL, LT = 2, SS = 0    -What are the planned order releases for Period 3? -What are the planned order releases for Period 3?

(Multiple Choice)
4.7/5
(30)

Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level. Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level.    -How many units of A will the company need to acquire in order to ship an order of 20 X's? -How many units of A will the company need to acquire in order to ship an order of 20 X's?

(Multiple Choice)
4.7/5
(39)

Q = 20, LT = 2, SS = 5 Q = 20, LT = 2, SS = 5    -What are the net requirements for Period 3? -What are the net requirements for Period 3?

(Multiple Choice)
4.9/5
(36)

Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level. Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level.    -How many units of B will the company need to acquire in order to ship an order of 20 X's? -How many units of B will the company need to acquire in order to ship an order of 20 X's?

(Multiple Choice)
4.7/5
(39)

Q = LFL, LT = 2, SS = 5 Q = LFL, LT = 2, SS = 5    -What are the planned order releases for Period 2? -What are the planned order releases for Period 2?

(Multiple Choice)
4.8/5
(41)

  -Determine the minimum number of weeks to make Part M, starting with no current inventories. -Determine the minimum number of weeks to make Part M, starting with no current inventories.

(Multiple Choice)
4.8/5
(29)

  -What is the projected on-hand inventory for Period 8? -What is the projected on-hand inventory for Period 8?

(Multiple Choice)
4.7/5
(45)

  -What are the net requirements for Period 8? -What are the net requirements for Period 8?

(Multiple Choice)
4.8/5
(42)

Q = LFL, LT = 2, SS = 0 Q = LFL, LT = 2, SS = 0    -What are the planned order releases for Period 1? -What are the planned order releases for Period 1?

(Multiple Choice)
4.8/5
(45)

  -Determine the quantity of Part C required to make 100 units of Part A. -Determine the quantity of Part C required to make 100 units of Part A.

(Multiple Choice)
4.7/5
(40)

Q = LFL, LT = 3, SS = 0 Q = LFL, LT = 3, SS = 0    -What are the planned order releases for Period 2? -What are the planned order releases for Period 2?

(Multiple Choice)
4.8/5
(32)

Q = 20, LT = 2, SS = 5 Q = 20, LT = 2, SS = 5    -What are the net requirements for Period 9? -What are the net requirements for Period 9?

(Multiple Choice)
4.8/5
(37)

Q = 20, LT = 2, SS = 5 Q = 20, LT = 2, SS = 5    -What are the planned order releases for Period 1? -What are the planned order releases for Period 1?

(Multiple Choice)
4.7/5
(38)

  -Determine the quantity of Part D required to make 100 units of Part A. -Determine the quantity of Part D required to make 100 units of Part A.

(Multiple Choice)
4.8/5
(30)

  -Determine the quantity of Part B required to make 100 units of Part A. -Determine the quantity of Part B required to make 100 units of Part A.

(Multiple Choice)
4.7/5
(43)

Q = LFL, LT = 2, SS = 0 Q = LFL, LT = 2, SS = 0    -What are the net requirements for Period 2? -What are the net requirements for Period 2?

(Multiple Choice)
4.8/5
(36)

Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level. Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level.    -How many units of E will the company need to acquire in order to ship an order of 20 X's? -How many units of E will the company need to acquire in order to ship an order of 20 X's?

(Multiple Choice)
4.8/5
(44)

  -What are the planned order releases for Period 6? -What are the planned order releases for Period 6?

(Multiple Choice)
4.9/5
(34)

Q = 20, LT = 2, SS = 5 Q = 20, LT = 2, SS = 5    -What is the projected on-hand inventory for Period 5? -What is the projected on-hand inventory for Period 5?

(Multiple Choice)
4.7/5
(34)

  -What are the net requirements for Period 5? -What are the net requirements for Period 5?

(Multiple Choice)
4.7/5
(32)
Showing 21 - 40 of 46