Exam 11: Managing Information Flowsmrp and ERP
Exam 1: Operations Management, Processes, and Supply Chain Management41 Questions
Exam 2: Corporate Strategy, Performance, and Sustainability55 Questions
Exam 3: Product Design and Development50 Questions
Exam 4: Process Design and Capacity Management48 Questions
Exam 5: Customer Relationships and Customer Service50 Questions
Exam 6: Demand Management, Forecasting, and Aggregate Planning45 Questions
Exam 7: Independent Demand Inventory Management45 Questions
Exam 8: Supplement: Job Scheduling and Vehicle Routing and Material Flow Analysis and Facility Layouts93 Questions
Exam 9: Lean Systems50 Questions
Exam 10: Managing Customer and Work Flows50 Questions
Exam 11: Managing Information Flowsmrp and ERP46 Questions
Exam 12: Managing Projects42 Questions
Exam 13: Supplement: Statistical Quality Control and Six Sigma Quality Management97 Questions
Exam 14: Supply Chain Processes50 Questions
Exam 15: Location, Logistics, and Product Returns49 Questions
Exam 16: Integrating Processes Along the Supply Chain42 Questions
Select questions type
Q = LFL, LT = 2, SS = 0
-What are the planned order releases for Period 3?

(Multiple Choice)
4.7/5
(30)
Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level.
-How many units of A will the company need to acquire in order to ship an order of 20 X's?

(Multiple Choice)
4.7/5
(39)
Q = 20, LT = 2, SS = 5
-What are the net requirements for Period 3?

(Multiple Choice)
4.9/5
(36)
Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level.
-How many units of B will the company need to acquire in order to ship an order of 20 X's?

(Multiple Choice)
4.7/5
(39)
Q = LFL, LT = 2, SS = 5
-What are the planned order releases for Period 2?

(Multiple Choice)
4.8/5
(41)
-Determine the minimum number of weeks to make Part M, starting with no current inventories.

(Multiple Choice)
4.8/5
(29)
Q = LFL, LT = 2, SS = 0
-What are the planned order releases for Period 1?

(Multiple Choice)
4.8/5
(45)
-Determine the quantity of Part C required to make 100 units of Part A.

(Multiple Choice)
4.7/5
(40)
Q = LFL, LT = 3, SS = 0
-What are the planned order releases for Period 2?

(Multiple Choice)
4.8/5
(32)
Q = 20, LT = 2, SS = 5
-What are the net requirements for Period 9?

(Multiple Choice)
4.8/5
(37)
Q = 20, LT = 2, SS = 5
-What are the planned order releases for Period 1?

(Multiple Choice)
4.7/5
(38)
-Determine the quantity of Part D required to make 100 units of Part A.

(Multiple Choice)
4.8/5
(30)
-Determine the quantity of Part B required to make 100 units of Part A.

(Multiple Choice)
4.7/5
(43)
Q = LFL, LT = 2, SS = 0
-What are the net requirements for Period 2?

(Multiple Choice)
4.8/5
(36)
Assume that the company using the following product structure tree has 5 items each at the 0 level, 10 items each at the 1 level, and 20 items each at the 2 level.
-How many units of E will the company need to acquire in order to ship an order of 20 X's?

(Multiple Choice)
4.8/5
(44)
Q = 20, LT = 2, SS = 5
-What is the projected on-hand inventory for Period 5?

(Multiple Choice)
4.7/5
(34)