Exam 12: Managing Projects
Exam 1: Operations Management, Processes, and Supply Chain Management41 Questions
Exam 2: Corporate Strategy, Performance, and Sustainability55 Questions
Exam 3: Product Design and Development50 Questions
Exam 4: Process Design and Capacity Management48 Questions
Exam 5: Customer Relationships and Customer Service50 Questions
Exam 6: Demand Management, Forecasting, and Aggregate Planning45 Questions
Exam 7: Independent Demand Inventory Management45 Questions
Exam 8: Supplement: Job Scheduling and Vehicle Routing and Material Flow Analysis and Facility Layouts93 Questions
Exam 9: Lean Systems50 Questions
Exam 10: Managing Customer and Work Flows50 Questions
Exam 11: Managing Information Flowsmrp and ERP46 Questions
Exam 12: Managing Projects42 Questions
Exam 13: Supplement: Statistical Quality Control and Six Sigma Quality Management97 Questions
Exam 14: Supply Chain Processes50 Questions
Exam 15: Location, Logistics, and Product Returns49 Questions
Exam 16: Integrating Processes Along the Supply Chain42 Questions
Select questions type
Following are the three estimates for a project:
-Calculate the expected completion time for Task B.

Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
A
A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk? 

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
E
Following are the three estimates for a project:
-Calculate the expected completion time for Task D.

Free
(Multiple Choice)
5.0/5
(37)
Correct Answer:
D
Following are the three estimates for a project:
-Calculate the completion time variance for Task C.

(Multiple Choice)
4.8/5
(33)
The table provides a project with the task lengths (in days) and precedence requirements.
-Calculate the late start (LS) time for Task C.

(Multiple Choice)
4.8/5
(36)
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
-Which of the following identifies the critical path tasks?

(Multiple Choice)
4.7/5
(35)
The table provides a project with the task lengths (in days) and precedence requirements.
-Based on the information, which of the following statements is true?

(Multiple Choice)
4.7/5
(33)
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
-Which task has the greatest amount of slack?

(Multiple Choice)
4.7/5
(35)
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
-Based on the information, what are the days to completion?

(Multiple Choice)
4.8/5
(36)
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
-What are the expected days to completion?

(Multiple Choice)
4.8/5
(36)
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
-Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost.

(Multiple Choice)
4.8/5
(39)
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path? 

(Multiple Choice)
4.8/5
(37)
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______. 

(Multiple Choice)
4.7/5
(36)
Following are the three estimates for a project:
-Calculate the completion time variance for Task D.

(Multiple Choice)
4.9/5
(44)
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
-What is the crash costs for Task A?

(Multiple Choice)
4.9/5
(35)
Following are the three estimates for a project:
-Calculate the expected completion time for Task O.

(Multiple Choice)
4.7/5
(38)
What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days? 

(Multiple Choice)
4.8/5
(35)
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
-Based on the information, which of the following statements is true?

(Multiple Choice)
4.9/5
(38)
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
-Calculate the late finish (LF) time for Task N.

(Multiple Choice)
4.9/5
(37)