Exam 12: Managing Projects

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Following are the three estimates for a project: Following are the three estimates for a project:    -Calculate the expected completion time for Task B. -Calculate the expected completion time for Task B.

Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
Verified

A

A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk? A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk?

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
Verified

E

Following are the three estimates for a project: Following are the three estimates for a project:    -Calculate the expected completion time for Task D. -Calculate the expected completion time for Task D.

Free
(Multiple Choice)
5.0/5
(37)
Correct Answer:
Verified

D

Following are the three estimates for a project: Following are the three estimates for a project:    -Calculate the completion time variance for Task C. -Calculate the completion time variance for Task C.

(Multiple Choice)
4.8/5
(33)

The table provides a project with the task lengths (in days) and precedence requirements. The table provides a project with the task lengths (in days) and precedence requirements.    -Calculate the late start (LS) time for Task C. -Calculate the late start (LS) time for Task C.

(Multiple Choice)
4.8/5
(36)

Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project. Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which of the following identifies the critical path tasks? -Which of the following identifies the critical path tasks?

(Multiple Choice)
4.7/5
(35)

The table provides a project with the task lengths (in days) and precedence requirements. The table provides a project with the task lengths (in days) and precedence requirements.    -Based on the information, which of the following statements is true? -Based on the information, which of the following statements is true?

(Multiple Choice)
4.7/5
(33)

Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project. Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which task has the greatest amount of slack? -Which task has the greatest amount of slack?

(Multiple Choice)
4.7/5
(35)

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates. The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Based on the information, what are the days to completion? -Based on the information, what are the days to completion?

(Multiple Choice)
4.8/5
(36)

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates. The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -What are the expected days to completion? -What are the expected days to completion?

(Multiple Choice)
4.8/5
(36)

The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs. The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost. -Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost.

(Multiple Choice)
4.8/5
(39)

A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path? A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path?

(Multiple Choice)
4.8/5
(37)

A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______. A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______.

(Multiple Choice)
4.7/5
(36)

Following are the three estimates for a project: Following are the three estimates for a project:    -Calculate the completion time variance for Task D. -Calculate the completion time variance for Task D.

(Multiple Choice)
4.9/5
(44)

The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs. The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -What is the crash costs for Task A? -What is the crash costs for Task A?

(Multiple Choice)
4.9/5
(35)

Following are the three estimates for a project: Following are the three estimates for a project:    -Calculate the expected completion time for Task O. -Calculate the expected completion time for Task O.

(Multiple Choice)
4.7/5
(38)

What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days? What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days?

(Multiple Choice)
4.8/5
(35)

Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown: Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true? -Based on the information, which of the following statements is true?

(Multiple Choice)
4.9/5
(38)

Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project. Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the late finish (LF) time for Task N. -Calculate the late finish (LF) time for Task N.

(Multiple Choice)
4.9/5
(37)

This Gantt chart can be used to show the following: This Gantt chart can be used to show the following:

(Multiple Choice)
4.7/5
(31)
Showing 1 - 20 of 42
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)