Exam 8: Aggregate Planning in a Supply Chain
Exam 1: Understanding the Supply Chain76 Questions
Exam 2: Supply Chain Performance: Achieving Strategic Fit and Scope75 Questions
Exam 3: Supply Chain Drivers and Metrics69 Questions
Exam 4: Designing Distribution Networks and Applications to e-Business75 Questions
Exam 5: Network Design in the Supply Chain75 Questions
Exam 6: Designing Global Supply Chain Networks75 Questions
Exam 7: Demand Forecasting in a Supply Chain73 Questions
Exam 8: Aggregate Planning in a Supply Chain76 Questions
Exam 9: Sales and Operations Planning: Planning Supply and Demand in a Supply Chain77 Questions
Exam 10: Coordination in a Supply Chain76 Questions
Exam 11: Managing Economies of Scale in the Supply Chain: Cycle Inventory75 Questions
Exam 12: Managing Uncertainty in a Supply Chain: Safety Inventory80 Questions
Exam 13: Determining the Optimal Level of Product Availability79 Questions
Exam 14: Transportation in a Supply Chain75 Questions
Exam 15: Sourcing Decisions in a Supply Chain77 Questions
Exam 16: Pricing and Revenue Management in a Supply Chain87 Questions
Exam 17: Sustainability and the Supply Chain75 Questions
Select questions type
Safety inventory is defined as inventory held to satisfy demand that is higher than forecasted.
(True/False)
4.9/5
(43)
Given that forecasts are always wrong to some degree, the aggregate plan needs to have some flexibility built into it if it is to be useful.
(True/False)
4.8/5
(35)
Scenario 8.2 - Willow
A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6.
January February March April May Forecast 400 800 1200 700 300 Beginning Inventory 100 Regular Time Qvertime Subcontracting Ending Inventory
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts.
-Without actually solving the aggregate planning problem, it is safe to conclude that in the optimal solution to Scenario 8.2.
(Multiple Choice)
4.9/5
(38)
Capacity used to satisfy demand that is higher than forecasted is
(Multiple Choice)
4.9/5
(34)
The strategy where a stable machine capacity and workforce are maintained with a constant output rate, with inventory levels fluctuating over time, is the
(Multiple Choice)
4.9/5
(40)
Scenario 8.1 - Gang Aft Agley
Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is $9 per unit, and the cost of carrying a unit in inventory from one month to the next is $2.
January February March April May Forecast 500 750 1200 650 300 Beginning Inventory 100 Regular Time Overtime Subcontracting Ending Inventory
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 300 units in any five month window. The plant capacity is 600 units per month produced using two shifts, regardless of the number of days in a month. By policy, management wants to avoid stockouts.
-Formulate the aggregate plan using linear programming.
(Essay)
4.8/5
(27)
Most strategies that an aggregate planner actually uses are in combination and are referred to as the
(Multiple Choice)
4.8/5
(39)
Scenario 8.2 - Willow
A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6.
January February March April May Forecast 400 800 1200 700 300 Beginning Inventory 100 Regular Time Qvertime Subcontracting Ending Inventory
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts.
-What is the optimal total cost of the aggregate plan developed to address Scenario 8.2?
(Multiple Choice)
4.9/5
(45)
Scenario 8.1-Gang Aft Agley
Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is $9 per unit, and the cost of carrying a unit in inventory from one month to the next is $2.
January February March April May Forecast 500 750 1200 650 300 Beginning Inventory 100 Regular Time Overtime Subcontracting Ending Inventory
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 300 units in any five month window. The plant capacity is 600 units per month produced using two shifts, regardless of the number of days in a month. By policy, management wants to avoid stockouts.
-Use the information from Scenario 8.1 to determine the number of decision variables in this scenario.
(Multiple Choice)
4.7/5
(30)
Scenario 8.1-Gang Aft Agley
Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is $9 per unit, and the cost of carrying a unit in inventory from one month to the next is $2.
January February March April May Forecast 500 750 1200 650 300 Beginning Inventory 100 Regular Time Overtime Subcontracting Ending Inventory
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 300 units in any five month window. The plant capacity is 600 units per month produced using two shifts, regardless of the number of days in a month. By policy, management wants to avoid stockouts.
-What is the optimal total cost of the aggregate plan developed to address Scenario 8.1?
(Multiple Choice)
4.7/5
(35)
Scenario 8.1-Gang Aft Agley
Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is $9 per unit, and the cost of carrying a unit in inventory from one month to the next is $2.
January February March April May Forecast 500 750 1200 650 300 Beginning Inventory 100 Regular Time Overtime Subcontracting Ending Inventory
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 300 units in any five month window. The plant capacity is 600 units per month produced using two shifts, regardless of the number of days in a month. By policy, management wants to avoid stockouts.
-Which of these is a constraint that is appropriate for Scenario 8.1?
(Multiple Choice)
4.9/5
(43)
Showing 61 - 76 of 76
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)