Slack is also known as __________.

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
Verified

C

An activity or event that, if delayed, will delay project completion is called a(n)__________.

Free
(Short Answer)
4.9/5
(37)
Correct Answer:
Verified

critical activity

Task H has duration of 5 days, an early start of 25 days, an early finish of 30 days, a late start of 25 days, and a late finish of 30 days. There are __________ days of slack for task H.

Free
(Short Answer)
5.0/5
(36)
Correct Answer:
Verified

0 days

The variance of a population is a measure of the population's __________.

(Multiple Choice)
4.8/5
(34)

The __________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.

(Short Answer)
4.9/5
(43)

__________ was developed by the U.S. Navy while the __________ was developed by __________.

(Multiple Choice)
4.8/5
(35)

The arrangement of all activities (and, in some cases, events)in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________.

(Short Answer)
4.8/5
(36)

The authors recommend preparing a schedule for each __________.

(Multiple Choice)
4.8/5
(30)

The _________ was developed by Henry Gantt in 1917.

(Short Answer)
5.0/5
(40)

Describe the benefits of forming a network of activity and event relationships that graphically portrays sequential relations between tasks in a project.

(Essay)
4.9/5
(30)

Explain the difference between Total Slack and Free Slack in a network.

(Essay)
4.9/5
(34)

Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a pessimistic duration of 30 days. If the optimistic and pessimistic durations are 95 percent estimates, the standard deviation for task J is ________ days.

(Short Answer)
4.9/5
(33)

The __________ for an activity is equal to the largest early finish for its preceding activities.

(Multiple Choice)
4.9/5
(34)

__________ have a weakness of being difficult to follow when multiple paths exist, but __________ are more helpful in the hands-on task of managing the project.

(Multiple Choice)
4.9/5
(38)

The authors define __________ as the time an activity can be delayed without affecting the start time of any successor activity

(Short Answer)
4.7/5
(34)

Any time two or more paths of a network come together, the probability of both paths being on time is the product of the probabilities for the individual paths. This scenario is referred to as __________.

(Short Answer)
4.8/5
(31)

A(n)__________ is a point where one or more lines (arrows)begin or terminate, commonly used for depicting an event or activity.

(Short Answer)
4.7/5
(36)

When using the beta distribution, the denominator of the formula for standard deviation should ________.

(Multiple Choice)
4.9/5
(44)

Explain why it is important to evaluate non-critical paths that possess large variances and/or path times that are close to critical in duration.

(Essay)
4.9/5
(39)

A __________ is a combination of interrelated activities and events depicted with arcs and nodes.

(Short Answer)
4.8/5
(28)