Exam 8: Scheduling
Exam 1: Projects in Contemporary Organizations41 Questions
Exam 5: The Project in the Organizational Structure49 Questions
Exam 2: Strategic Management and Project Selection39 Questions
Exam 3: The Project Manager44 Questions
Exam 4: Negotiation and the Management of Conflict44 Questions
Exam 6: Project Activity Planning39 Questions
Exam 7: Budgeting and Cost Estimation40 Questions
Exam 8: Scheduling50 Questions
Exam 9: Resource Allocation46 Questions
Exam 10: Monitoring and Information Systems53 Questions
Exam 11: Project Control41 Questions
Exam 12: Project Auditing52 Questions
Select questions type
An activity or event that, if delayed, will delay project completion is called a(n)__________.
Free
(Short Answer)
4.9/5
(37)
Correct Answer:
critical activity
Task H has duration of 5 days, an early start of 25 days, an early finish of 30 days, a late start of 25 days, and a late finish of 30 days. There are __________ days of slack for task H.
Free
(Short Answer)
5.0/5
(36)
Correct Answer:
0 days
The variance of a population is a measure of the population's __________.
(Multiple Choice)
4.8/5
(34)
The __________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.
(Short Answer)
4.9/5
(43)
__________ was developed by the U.S. Navy while the __________ was developed by __________.
(Multiple Choice)
4.8/5
(35)
The arrangement of all activities (and, in some cases, events)in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________.
(Short Answer)
4.8/5
(36)
The authors recommend preparing a schedule for each __________.
(Multiple Choice)
4.8/5
(30)
Describe the benefits of forming a network of activity and event relationships that graphically portrays sequential relations between tasks in a project.
(Essay)
4.9/5
(30)
Explain the difference between Total Slack and Free Slack in a network.
(Essay)
4.9/5
(34)
Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a pessimistic duration of 30 days. If the optimistic and pessimistic durations are 95 percent estimates, the standard deviation for task J is ________ days.
(Short Answer)
4.9/5
(33)
The __________ for an activity is equal to the largest early finish for its preceding activities.
(Multiple Choice)
4.9/5
(34)
__________ have a weakness of being difficult to follow when multiple paths exist, but __________ are more helpful in the hands-on task of managing the project.
(Multiple Choice)
4.9/5
(38)
The authors define __________ as the time an activity can be delayed without affecting the start time of any successor activity
(Short Answer)
4.7/5
(34)
Any time two or more paths of a network come together, the probability of both paths being on time is the product of the probabilities for the individual paths. This scenario is referred to as __________.
(Short Answer)
4.8/5
(31)
A(n)__________ is a point where one or more lines (arrows)begin or terminate, commonly used for depicting an event or activity.
(Short Answer)
4.7/5
(36)
When using the beta distribution, the denominator of the formula for standard deviation should ________.
(Multiple Choice)
4.9/5
(44)
Explain why it is important to evaluate non-critical paths that possess large variances and/or path times that are close to critical in duration.
(Essay)
4.9/5
(39)
A __________ is a combination of interrelated activities and events depicted with arcs and nodes.
(Short Answer)
4.8/5
(28)