Exam 12: Project Auditing

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Research by Walker et al argues that __________ is essential for management's ability to assemble information that is both timely and accurate.

Free
(Short Answer)
4.8/5
(37)
Correct Answer:
Verified

independence

Which of the following is not one of the top three project success factors, from a project manager's perspective?

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
Verified

C

The __________ dimension of project success includes factors relating to opening a new market, developing a new line of products or services. Alternatively, if an internal project, success factors include developing new technologies, skills, or competencies.

Free
(Multiple Choice)
5.0/5
(37)
Correct Answer:
Verified

D

If a detailed audit cannot be completed because the auditor does not possess the technical knowledge needed, a __________ audit is required.

(Short Answer)
4.7/5
(34)

The stated project objectives, including customer satisfaction, are part of the project's __________ goals

(Short Answer)
4.9/5
(32)

Contact between the a/e team and the __________ are not made without clearance from senior management.

(Short Answer)
4.8/5
(33)

Discuss the differences between a project audit and a financial audit.

(Essay)
4.8/5
(39)

__________ is one of the four dimensions of project success, and is focused on meeting both the budget and schedule established in the project plan.

(Multiple Choice)
4.8/5
(33)

Project morale may suffer if the project audit report is not written with a __________.

(Short Answer)
4.9/5
(38)

__________ is defined as a standard for performance, commonly established early on for later comparisons.

(Multiple Choice)
4.9/5
(32)

In order for an audit/evaluation team to be conducted with skills and precision, all of the following conditions must be met, EXCEPT __________.

(Multiple Choice)
4.8/5
(36)

A major vehicle for evaluation is the __________, which is a more or less formal inquiry into any aspect of the project.

(Short Answer)
4.7/5
(33)

The __________ section of the audit report should contain a review of major risks associated with the project and their projected impact on project time/cost/performance.

(Short Answer)
4.9/5
(33)

In the Future Project Status section of the audit report, no assumptions should be made about __________ that are still under investigation at the time of the audit.

(Short Answer)
4.8/5
(41)

The __________ section of the audit should be reported as of the time of the audit. It should contain the following measures of performance: cost, schedule, progress, and quality.

(Short Answer)
4.8/5
(35)

__________ tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.

(Short Answer)
4.8/5
(23)

The __________ goals are usually not overtly identified..

(Short Answer)
4.8/5
(34)

__________ appraises the progress and performance of a project compared to that project's planned progress and performance, or compared to the progress and performance of other, similar projects.

(Multiple Choice)
4.9/5
(45)

If the audit report is to serve as a communication device, there must be a __________ for such documents.

(Short Answer)
4.9/5
(38)

The value of project audits/evaluations conducted during the post-project stage will depend on the __________ to future projects.

(Short Answer)
4.9/5
(39)
Showing 1 - 20 of 52