Exam 8: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The use of PERT (ADM)has declined sharply in recent years because a large majority of project management software __________.

(Multiple Choice)
4.9/5
(37)

The series of connected activities (or intermediate events)between any two events in a network is called __________.

(Short Answer)
4.8/5
(34)

The calculation of the standard deviation for the beta distribution is based on the assumption that __________.

(Multiple Choice)
4.9/5
(30)

In AOA networks, an activity of zero duration is called a(n)________.

(Short Answer)
4.9/5
(29)

Task F has duration of 10 days and an earliest start date of 20 days. Based on the given data, determine the early finish duration for task F.

(Multiple Choice)
4.8/5
(30)

Using precedence diagramming methods, activity B must not start until after activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. This relationship between activities A and B is an example of a(n)__________.

(Short Answer)
4.9/5
(31)

__________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.

(Short Answer)
4.7/5
(37)

Which of the following is NOT an advantage of a Gantt chart?

(Multiple Choice)
4.7/5
(43)

In the AOA network, circles depict ________.

(Multiple Choice)
4.9/5
(31)

Explain the meaning of slack in a network.

(Essay)
4.8/5
(34)
Showing 41 - 50 of 50
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)