Exam 12: Systems Development: Investigation and Analysis
Exam 1: An Introduction to Information Systems85 Questions
Exam 2: Information Systems in Organizations85 Questions
Exam 3: Hardware: Input, Processing, and Output Devices85 Questions
Exam 4: Software: Systems and Application Software85 Questions
Exam 5: Database Systems, Data Centers, and Business Intelligence85 Questions
Exam 6: Telecommunications and Networks82 Questions
Exam 7: The Internet, Web, Intranets, and Extranets85 Questions
Exam 8: Electronic and Mobile Commerce85 Questions
Exam 9: Enterprise Systems85 Questions
Exam 10: Information and Decision Support Systems85 Questions
Exam 11: Knowledge Management and Specialized Information Systems85 Questions
Exam 12: Systems Development: Investigation and Analysis85 Questions
Exam 13: Systems Development: Design, Implementation, and Review85 Questions
Exam 14: The Personal and Social Impact of Computers89 Questions
Select questions type
During the _____ phase of the systems development life cycle, people attempt to answer the questions "What must the information system do to solve the problem?"
(Multiple Choice)
4.9/5
(42)
Information systems planning translates strategic and organizational goals into systems development initiatives.
(True/False)
4.8/5
(41)
________ is an iterative systems development approach developed by IBM and includes a number of tools and techniques that are typically tailored to fit the needs of a specific organization.
(Multiple Choice)
4.8/5
(39)
The systems development team, is responsible for determining the information system objectives and delivering a system that meets those objectives.
(True/False)
4.8/5
(35)
______ is a technique used to describe how data can flow between objects.
(Multiple Choice)
4.8/5
(33)
The ______ consists of all project activities that, if delayed, would delay the entire project.
(Multiple Choice)
4.9/5
(36)
The purpose of the ______ phase of the traditional system development process is to answer the questions "How will the information system do what it must do to obtain the solution?"
(Short Answer)
4.8/5
(35)
The _____ system development approach requires cooperation and frequent face-to-face meetings with all project participants as they modify, refine, and test how the system meets users' needs and what its capabilities are.
(Multiple Choice)
4.8/5
(40)
Identify the five phases of a traditional systems development project and state the goal of each phase.
(Essay)
4.8/5
(36)
Proper planning can guarantee that projects will not fall behind schedule, go over budget, or not meet expectations.
(True/False)
4.9/5
(34)
The use case diagram is technique associated with ______ systems analysis.
(Short Answer)
4.8/5
(29)
Data collection begins by identifying the various sources of data, including both ______ sources.
(Multiple Choice)
4.9/5
(24)
The system analysis concludes with a formal system analysis report that includes ____.
(Multiple Choice)
4.8/5
(42)
During the ____ phase of the system development process, potential problems and opportunities are identified and considered in light of the goals of the business.
(Multiple Choice)
4.8/5
(40)
______ is a systems development approach that stresses agile, incremental development with a team of a dozen or fewer people who perform all systems development activities.
(Multiple Choice)
4.8/5
(39)
A project manager is a person that performs all of the system development roles, including systems analyst, programmer, and technical specialist.
(True/False)
4.9/5
(36)
______ are people who, either themselves or through the organization they represent, ultimately benefit from the systems development project.
(Short Answer)
4.8/5
(42)
Based on _____, managers make decisions regarding the initiation of each system investigation for potential IS projects.
(Multiple Choice)
4.9/5
(30)
____________________ is the amount of time a project activity can be delayed without delaying the entire project.
(Short Answer)
4.8/5
(35)
Showing 41 - 60 of 85
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)