If CPI = 1.05,then __________ is favorable.

(Multiple Choice)
4.9/5
(37)

EV - PV = __________.

(Multiple Choice)
4.9/5
(36)

Describe the three common difficulties in designing project reports.

(Essay)
4.8/5
(33)

What is the most likely project report to be issued periodically?

(Multiple Choice)
5.0/5
(43)

For project management,there are three distinct types of reports.Which of the following would be used in response to a special problem?

(Multiple Choice)
4.9/5
(47)

If EV = $500,AC = $475,PV = $450; SV = ________.

(Multiple Choice)
4.8/5
(45)

Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?

(Multiple Choice)
4.8/5
(40)

Monitoring,as an activity,should be kept distinct from __________,which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

(Multiple Choice)
4.7/5
(41)

The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.

(Multiple Choice)
4.8/5
(40)

Conceptually,EAC represents the amount spent to date plus __________.

(Multiple Choice)
4.9/5
(42)

Monitoring,as an activity,should be kept distinct from __________,which is the process of making judgments about the quality and effectiveness of project performance.

(Multiple Choice)
4.9/5
(38)

In earned value Analysis,the 50-50 rule assumes that __________.

(Multiple Choice)
4.9/5
(27)

The most common mistake made when monitoring data is to gather information that is clearly related to project performance but __________.

(Multiple Choice)
4.8/5
(40)